Equipment and Cable Installation for Metropolis
®
DMXtend
Shelf Horizontal Bay Mount
1000BASE-SX/LX Optical Fiber Cable
Installation
1 - 8 4
Lucent Technologies - Proprietary
See notice on first page
365-372-327 R2.0
Issue 1, October 2003
Procedure
Step 1
Refer to the engineering job specification. Determine the function slot
that the pack will be inserted. The 1GSX or 1GLX (LNW67 or
LNW68) pack can be inserted into function slots D1 or G1.
............................................................................................................................................................................
Step 2
Label the optical fiber cables, indicating bay, shelf, function group,
pack, and direction (
IN
or
OUT
).
............................................................................................................................................................................
Step 3
Route optical fiber cables from the interconnecting equipment into the
left side of the Metropolis
®
DMXtend and into the 1000BASE-SX/LX
optical ports.See Table 1-27, Optical Fiber routing (page 1-77)
............................................................................................................................................................................
Step 4
Place the optical fiber cables in a protective tube or channel.
............................................................................................................................................................................
Step 5
Check off the appropriate box in Appendix E, Installation Checklist.
...........................................................................................................................................................................
End of Steps