Operational Tests
Manual Switching Tests
5 - 1 6
Lucent Technologies - Proprietary
See notice on first page
365-372-327 R2.0
Issue 1, October 2003
............................................................................................................................................................................
Step 8
Use the scroll bar in the
Command Builder
window to scroll down to
the
rtrv-state-path
command.
............................................................................................................................................................................
Step 9
Click on the
rtrv-state-path
command.
............................................................................................................................................................................
Step 10
Click
Send
to issue the command.
Requirement:
The Response Window should display the command
followed by a
COMPLD
indication as well as indicating that the ring that
was active in Step 3 is no longer active and the other ring is now active.
............................................................................................................................................................................
Step 11
Repeat Step 4 through Step 10 to verify a switch back to the original
ring.
............................................................................................................................................................................
Step 12
Check off the appropriate box in Appendix E, Installation Checklist.
...........................................................................................................................................................................
End of Steps