Ring Setup and Testing: Integration Procedures
Manual Switching Tests
...........................................................................................................................................................................................................................................................
6 - 1 5
Lucent Technologies - Proprietary
See notice on first page
365-372-327 R2.0
Issue 1, October 2003
Function Units/Growth
Slots, Switching Test
Description
This test will initiate switching commands from the CIT TL1
Command Builder and verify proper switching and LED indications.
Important!
This procedure should be performed on each Function
Unit and/or Growth Slot pair.
Step 1
Use the scroll bar in the
Command Builder
window to scroll down to
the
rtrv-state-eqpt
command.
............................................................................................................................................................................
Step 2
Click on the
rtrv-state-eqpt
command.
............................................................................................................................................................................
Step 3
Click
Send
to issue the command.
Result:
The
Response Window
should display the command
followed by a
COMPLD
indication as well as indicating which
Function Unit and/or Growth Slot circuit pack is active and which is
standby.
This information should agree with the
ACTIVE
LEDS on the
LNW6/LNW7, LNW16, LNW39 circuit packs.
Important!
Equipment protection switching is not supported on
the LNW36(R1.1) and LNW46(R1.1) OLIUs.
............................................................................................................................................................................
Step 4
Note which Function Unit or Growth Slot circuit pack is the active
circuit pack from the previous result.
............................................................................................................................................................................
Step 5
Use the scroll bar in the
Command Builder
window to scroll down to
the
sw-toprotn-eqpt
command.
Important!
Equipment protection switching is not supported on
the LNW36(R1.1) and LNW46(R1.1) OLIUs.
............................................................................................................................................................................
Step 6
Click on the
sw-toprotn-eqpt
command.