363-205-401
RT Turn Up:
Issue 7, March 1997
Page 1 of 6
DLP-515
Install Line Switch Unit (LSU) in Facility Shelf
1.
NOTE:
An AUA13 LSU cannot be used in an RT channel bank assembly
equipped for FPD operation.
Get one LSU (Line Switch Unit) (AUA13 or AUA73) and inspect for possible
damage.
2.
Is the LSU an AUA13?
If YES, then proceed to Step 6.
If NO, then continue with Step 3.
3.
Is LSU being installed in RT channel bank assembly equipped for FPD capa-
bility?
If YES, then continue with Step 4.
If NO, then proceed to Step 5.
4.
Set switch S2 located on the side of the LSU circuit pack (Figure 1) to position
32 and proceed to Step 6.
5.
Set switch S2 located on the side of the LSU circuit pack (Figure 1) to position
64.