Conversions: NTP-010
363-205-401
Page 6 of 6
Issue 7, March 1997
DO ITEMS BELOW IN ORDER LISTED
FOR DETAILS, GO TO
15. Perform RT LED test.
16. Remove the ADU and set switches S1-3 and S1-4 to ABI and
CDI. Reinstall the ADU.
The MJ and FE LEDs on the ADU and DIGROUP LEDs on the
BCU light.
17. Wait for the switch personnel to restore to service the IFACs
associated with the RT.
As each IFAC is restored to service, the DIGROUP LED on the
BCU associated with the IFAC goes off. After all the DIGROUP
LEDs go off, a MN and FE remains lighted until the protection
IFAC is restored.
18. Wait for the switch personnel at the MCC to provision the RT.
Response:
Wait for the MCC to display EXC RT PROV
TYPE=ALL SID=g LRT= d e f COMPLETED - NO
TASKS PENDING (where g=Site ID number, d=SM
number, e=IDCU number, and f=FP303 RT number)
before continuing. Provisioning can take up to 15
minutes depending on the switch activity level.
19.
NOTE:
The next three steps verify correct end-to-end operation.
Test alarm system for power minor and fan alarms.
20. Test alarm system for miscellaneous alarms.
21. Perform channel tests.
22. Update office records.