363-205-401
Power Up: NTP-008
Issue 7, March 1997
Page 3 of 4
DO ITEMS BELOW IN ORDER LISTED
FOR DETAILS, GO TO
4.
NOTE:
Two BFUs are required to turn up each dual bank assembly;
one is needed for the dual bank assembly and the second
one is needed for the associated optical shelves. All 4 BFUs
should be installed at this time.
Install and check fuses in 4 BFUs (bank fuse units) in optics
power shelf.
5.
NOTE:
Only AUA11B or later version PCUs should be installed in
optics power shelf.
Install 8 PCUs in optics power shelf.
6.
Install A/FCU (alarm/fan control unit) in optics power shelf.
7.
Install AYB1B OUs in optical shelf.
8.
Update Office records.