363-205-401
Power Up:
Issue 7, March 1997
Page 1 of 6
DLP-504
Perform Test of RT Batteries Using 197A Battery
Load Test Set
1.
!
CAUTION:
Service interruption will occur if batteries are disconnected and AC power
is not available.
Obtain 197A BATTERY LOAD TEST SET (197A) and place near batteries to
be tested (Figure 1).
2.
NOTE:
The 197A test set is intended to test batteries that are fully charged. A
minimum of two days must be allowed between the time the batteries
(new or replacement) are put on high rate charge and this test is made.
After testing is completed, the batteries must be put on high rate charge
using the 337A BATTERY CHARGER.
Remove cover from 197A test set.
3.
Check 197A test set for proper operation (if not already performed).
Reference:
DLP-533
4.
Ensure that system(s) associated with batteries to be tested has AC power
available (PMN or P/M indicator on BCU circuit pack not lighted).