Before starting up after maintenance or repair work
●
check that all screw connections have been done up tightly
●
and ensure that any tank covers, screens or filters have been put back in
place
Ensure after finishing the maintenance or repair work and before starting
production again that
●
all the materials, tools and other equipment that was required for the
maintenance or repair work has been removed from the working area of the
machine.
●
any liquids that may have escaped have been removed
●
all the safety devices of the machine function properly.
1.7
Complying with the environmental protection regulations
Comply with the legal requirements for avoiding waste and proper
recycling/disposal in all work on the machine.
Especially when carrying out installation, maintenance and repair work,
substances that are a hazard to water such as
●
greases and oils
●
hydraulic oils
●
coolants
●
cleaners containing solvents
do not pollute the ground or get into the sewer system. These substances must be
stored, transported, collected and disposed of in suitable containers.
2
Intended Use
Grinders for abrasive wheels are used to machine metals, for example, for deburring, smoothing
down weld seams or to machine cast parts.
3
Installation
●
Blow out the compressed air line and hose before connecting the machine.
●
Ensure that all the lines have sufficiently large cross-sections (see section
Technical Data
) and
that the lines are not kinked or pinched. The compressed air hoses should only be longer than 3
m in exceptional cases.