6 Install the Product
LUMINELL SWEDEN AB
31
6.4 HOW TO COMMISSION THE PRODUCT
Before powering up the unit, make sure that all boxes in 6.4.1 below is marked with Yes.
If No, make a comment and correct before powering up the unit.
Physical and electrical installation checklist.
After above checkpoints are verified the system should be started up as per this
User’s Manual.
Operational and features function checklist:
Pos. Check points
Yes No
Comment
1
Press any button to awaken the Operator
Panel. Check display screen and signs.
2
Steer the searchlight up-/down-/port-
/starboard-wise into a safe heading.
3
Turn on the light and confirm:
spot beam working
Flood beam working
Dimfunction working
5
Network check - Operate all searchlights from
all Operator panels. Center, PS, SB, Aft.
6
Name the searchlight
7
Check and adjust Origin
Set the park position
8
If more than one searchlight installed:
Activate Synchronized control and confirm
that all searchlights are mowing.
Pos. Check points
Yes No Comment
1
Are the outgoing cables from the searchlight
undamaged with the radius smooth and not
stressed?
2
Are LAN cables placed/laid to not interfere
from high power cables?
3
Are Electrical connections made according to
manufacturer original electrical drawings and
wiring diagram?
4
The remote panel (OP) is screwed into bridge
panel, mounted in an IP56 environment. If
placed outdoors it must be under a protection
hood when not in use.
Summary of Contents for SL1
Page 7: ...LUMINELL SWEDEN AB 7 ...
Page 19: ...6 Install the Product LUMINELL SWEDEN AB 19 Mechanical drawing SL1 ...
Page 20: ...6 Install the Product LUMINELL SWEDEN AB 20 Mechanical drawing SL1 base measurements ...
Page 21: ...6 Install the Product LUMINELL SWEDEN AB 21 6 2 MECHANICAL INSTALLATION OF OPERATOR PANEL ...
Page 22: ...6 Install the Product LUMINELL SWEDEN AB 22 Mechanical drawing Operator panel ...
Page 23: ...6 Install the Product LUMINELL SWEDEN AB 23 Mechanical drawing Operator panel base ...
Page 24: ...6 Install the Product LUMINELL SWEDEN AB 24 6 3 SL1 ELECTRICAL SL1 electrical system overview ...
Page 26: ...6 Install the Product LUMINELL SWEDEN AB 26 Connection example 2 24Vdc ...
Page 66: ...12 Declaration of conformity CE LUMINELL SWEDEN AB 66 12 DECLARATION OF CONFORMITY CE ...
Page 67: ...13 type approval certificate DNV LUMINELL SWEDEN AB 67 13 TYPE APPROVAL CERTIFICATE DNV ...
Page 68: ...13 type approval certificate DNV LUMINELL SWEDEN AB 68 ...
Page 69: ...13 type approval certificate DNV LUMINELL SWEDEN AB 69 NOTES ...
Page 70: ...13 type approval certificate DNV LUMINELL SWEDEN AB 70 NOTES ...
Page 71: ...13 type approval certificate DNV LUMINELL SWEDEN AB 71 NOTES ...
Page 72: ...Luminell Sweden AB Seldonsvägen 8 SE 302 62 Halmstad Sweden Phone 46 35 38280 www glamox com ...