Installation - Site Preparation 

Installation - Drain Assembly

• 

Provide sufficient floor support. Check the floor at the installation site and make repairs as 

needed.

• 

Waterproof the floor is highly recommended. Finished floor must be level.

•  Provide adequate clearance on all sides of the bathtub.

• 

Minimum of 2 inch waste drain pipe is required.

NOTICE: It is recommended to dry fit the parts before installation.

1. 

Place a large drop cloth on the floor to protect the bathtub.

2. 

With help, lift the bathtub and place it on its side. Secure the bathtub to prevent it from moving.

3. 

Connect the 1 1/2” femail adapter as shown in figure 1. Wrap PTFE tape to the thread on the 

drain body and connect the adapter.

4. 

Upright the bathtub and carefully move it to the final installation position. (

NOTICE:

 Do not drag 

the bathtub on the floor as it will damage the bathtub.)

5.  Connect the drain assembly to the waste drain pipe. (

NOTICE:

 additional connectors and pipes 

are needed to complete the installation.)

Drain Body

Flange Gasket

Overflow

Overflow Channel

1 1/2” ABS Female Adapter

(included)

Waste Drain Pipe (not included)

Drain Gasket

Locking Nut

NOTE: 

Drain assembly is pre-installed on the bathtub. 

Install the included 1 1/2” female adapter first and connect 

the drain to the waste pipe. (Additional adapter or pipe will 

be required to complete the installation)

Fig. 1