1.  Begin by installing element #11, the smallest element. Locate the bag of twenty (20) HD CRA-

DLES with 7/8” radius to fit the 7/8” fiberglass rods. These cradles have clearance holes for 5/16” 
diameter bolts.  Drop four (4) 5/16-24 x 4” bolts down through the element #11 mounting plate. 
Hold the center of element #11 up near the plate and place two saddles on the center of 7/8” fi-
berglass rod. Raise the element up and feed the bolts down through the cradles. Place another 
cradle under each upper cradle and add locknuts. Tighten up the nuts until the element is almost 
secure. Then center the element through the cradles and rotate the element until the bolts at the 
element butt are up and their corresponding nuts are down.  Tighten the cradle bolts evenly and 
completely. Now orient the PHASE LINE CLAMP ASSEMBLIES on the element butts so the 
PHASING LINE CLAMP CAP are DOWN and square with the boom.  

 
2.  Continue mounting element #10, #9, #8, and #7 in order as described above. 

 

3.  Element #6 is different only as it has a 1” fiberglass rod and (4) HD CRADLES with 1” radius, fit-

ting the fiberglasss rod perfectly. Use (4) 5/16-24 x 4” bolts and locknuts to secure the element. 

 
4.   Element #5 and #4 both use 1-1/4” fiberglass rods and (4) HD CRADLES with 1-1/4” radius.  

Use 5/16-24 x 4-1/2” bolts and locknuts.  

 
5.  Because of their size and weight we have suggested that just the INNER SECTIONS of element 

#3, #2, and #1 be mounted before the whole element is assembled.  Element #3 and #2 use 2” 
fiberglass rods and (4) HD CRADLE with 2” radius. These cradles require 3/8-24 x 5” bolts and 
locknuts. Before tightening cradles completely be sure to rotate the element so the 3/8” PHASE 
LINE CLAMP CAPS are down and their bolts are perfectly perpendicular with the TOWER 
BOOM legs. Doing this will facilitate the installation of the phasing lines in the subsequent as-
sembly steps. 

 
6.   Element #1 uses a 2” fiberglass rod and (8) HD CRADLES with 2” radius.  These cradles require 

(8) 3/8-24 x 5” bolts and locknuts.  Again center and rotate the element in the cradles so the 3/8” 
PHASE LINE CLAMP CAPS are down and their bolts perpendicular to the TOWER BOOM legs. 
 

7. 

OPTIONAL

: THE TIP SECTION OF ELEMENTS #3, #2, AND #1 CAN NOW BE INSTALLED.   

You may also elect to do the element tip installation just prior to the antenna being place on a 
tower.  If you do it now or later, refer again to the appropriate element assembly sheet for the 
hardware required to attach the tip sections.  

 
8.  Now do the final check and tightening of the all elements forward to the Element #11.  TIGHTEN 

each bottom cradle EVENLY AND SECURELY. 

6-30LP11 ELEMENT INSTALLATION 

Summary of Contents for 6-30LP11

Page 1: ...trically Top quality materials combined with many CNC machined parts will keep it trouble free for years or operation Performance is excellent and specific path gain can be as much as 12 dB with groun...

Page 2: ...nd position it about 3 4 inside the other 1 4 hole Repeat this for all five of the 7 8 FIBERGLASS RODS Slight repositioning of the poly discs may be required when the element is mounted below the boom...

Page 3: ...8 OUTSIDE SLEEVE over the butt section to maintain element strength to survive 125 mph winds ELEMENT 4 is unique because at 4 there is transition in phasing line diameter Both PHASE LINE CLAMPS AND 3...

Page 4: ...reign substances that could conduct under the right condition 8 Assembling ELEMENT 2 1 is similar to 3 except ELEMENT 2 1 each use 2 ELEMENT SIDE SUPPORT BRACKETS that are attached to the 2 sections j...

Page 5: ...2 grade 5 galvanized bolts 1 2 13 galvanized nut 1 2 13 galvanized pal nut for all tower boom section joints 2 Shims as shown are supplied with tower sections to help align Use as needed 6 30LP11 BOOM...

Page 6: ...6 30LP11 ELEMENT ASSEMBLY 4 11...

Page 7: ...6 30LP11 ELEMENT ASSEMBLY 3...

Page 8: ...6 30LP11 ELEMENT ASSEMBLY 2...

Page 9: ...6 30LP11 ELEMENT ASSEMBLY 1...

Page 10: ...fiberglass rods and 4 HD CRADLES with 1 1 4 radius Use 5 16 24 x 4 1 2 bolts and locknuts 5 Because of their size and weight we have suggested that just the INNER SECTIONS of element 3 2 and 1 be moun...

Page 11: ...kle eye and over the cable eye Push the cable end back through the clips pull all the slack out of the cable and then push one clip close against the cable eye and begin tightening the nuts on the cli...

Page 12: ...t PHASE LINE CLAMPS only 3 Continue by adding the next set of phasing lines between element 10 and 9 Center align the phasing rods and tighten the PHASE LINE CLAMPS on element 10 Contin ue installing...

Page 13: ...o pairs of 3 8 PHASE LINE CLAMP CAPS on the element butts If not then add them now loosely Continue installing this phase line set using eight 8 3 8 PHASE LINE SUPPORT INSULATORS Center and align the...

Page 14: ...boom itself Slide two 3 8 cable clips on a cable end and route the cable through the turnbuckle over the cable eye and back through the two clips Slide one clip against the cable eye and begin tighte...

Page 15: ...INSULATOR 2 I D 2 CRADLE 2 HD MACH ALUM 8 ELEMENT VERTICAL SUPPORT MAST 1 1 2 X 48 WELDED 1 ELEMENT VERTICAL SUPPORT BRACKET STEEL WELDED 1 ELEMENT SIDE SUPPORT BRACKET ALUMINUM WELDED 2 3 8 PHASE LIN...

Page 16: ...INSULATOR 2 I D 2 CRADLE 2 HD MACH ALUM 4 ELEMENT VERTICAL SUPPORT MAST 1 1 2 X 48 WELDED 1 ELEMENT VERTICAL SUPPORT BRACKET STEEL WELDED 1 ELEMENT SIDE SUPPORT BRACKET WELDED 2 3 8 PHASE LINE CLAMP...

Page 17: ...7 8 X 058 X 71 875 6063 T832 2 ELE 3 SEC 7 3 4 X 049 X 81 SOE 6063 T832 2 ELE 3 SEC 8 1 2 X 049 X 63 6063 T832 2 CENTER SUPPORT INSUL 2 X 36 W COUPLING RINGS 1 POLY DISC INSULATOR 2 I D 2 CRADLE 2 HD...

Page 18: ...T MAST 1 2 X 180 X 96 GALV GUY CABLE HPTG 6700 PHILISTRAN X 70 FT 1 TURNBUCKLE 1 2 X 12 FORGED GALV 2 CRADLE 1 1 2 MACHINED ALUM 13 32 HOLES 16 TOWER SHIM THICK 12 TOWER SHIM THIN 12 HARDWARE BOLT 1 2...

Page 19: ...T6 2 3 16 X ROD BENT 6061 T6 2 PHASE LINE SUPPORT INSULATOR FOR 3 8 TUBE 24 PHASE LINE SUPPORT INSULATOR FOR 3 16 ROD 20 PHASE LINE SUPPORT CAP DELRIN 44 375 PHASE LINE SPACER 3 4 X 2 X 2 DELRIN 3 18...

Page 20: ...1 1 X 058 X 60 SOE 1 4 HOLE 8 ELE 6 SEC 2 1 X 058 X 60 SOE 2 HOLES 2 ELE 4 SEC 4 1 X 058 X 39 SOE 4 SLEEVE 7 8 X 058 X 15 2 ELE 8 SEC 2 3 4 X 049 X 63 STR 2 ELE 9 SEC 2 3 4 X 049 X 39 25 STR 2 ELE 4 S...

Page 21: ...20 X 1 1 2 SS 10 SCREW 1 4 20 X 1 FH SS 16 NUT LOCKING 1 4 20 SS 32 SCREW 8 32 X 2 SS 10 SCREW 8 32 X 1 3 4 SS 10 SCREW 8 32 X 1 1 2 SS 22 SCREW 8 32 X 1 1 4 SS 28 SCREW 8 32 X 1 SS 16 LOCKNUT 8 32 SS...

Page 22: ...6 30LP11 PARTS IDENTIFICATION...

Page 23: ...20 X 2 1 4 SS 4 BOLT 1 4 20 X 2 SS 2 BOLT 1 4 20 X 1 1 2 SS 4 SCREW FLATHEAD 1 4 20 X 1 SS 4 NUT LOCKING 1 4 20 SS 24 SCREW 8 32 X 2 1 4 SS 2 SCREW 8 32 X 2 SS 4 SCREW 8 32 X 1 3 4 SS 4 SCREW 8 32 X...

Reviews: