BEFORE YOU BEGIN: Look over the ELEMENT ASSEMBLY sheets to get familiar with the various 
parts of the log periodic.  These written instructions attempt to give some order and efficiency to the 
overall assembly and make you aware of critical areas.  TWO CUPS OF ZINC PASTE HAS BEEN 
PROVIDED AND SHOULD BE USED AT EACH JOINT WHERE MACHINED PARTS JOIN 
ALUMINUM RODS OR TUBES AND GENERALLY AT EACH ELECTRICAL CONNECTION POINT. 

WE ALSO STRONGLY RECOMMEND THAT EACH BOLT AND SCREW USED, BE TOUCHED IN 
THIS PASTE WITH THE FIRST FEW THREADS.  THIS WILL PREVENT GAULING AND BETTER 
TIGHTENING OF THE STAINLESS HARDWARE

 
THIS IS A VERY LARGE ANTENNA WHEN COMPLETELY ASSEMBLED.  WE SUGGEST YOU 
ASSEMBLE THE ELEMENTS FIRST AND WHEN DOING THE LARGER ELEMENTS, ASSEMBLE 
THE TIP SECTIONS UP TO THE 1-1/2” SECTIONS, MARK AND SET ASIDE UNTIL THE BOOM IS 
ASSEMBLED AND THE INNER SECTIONS 2” DIAMETER AND LARGER ARE MOUNTED ON 
THE BOOM.   
 
THE LONGEST 3 ELEMENTS ARE BOXED INDIVIDUALLY TO MAKE IT EASIER TO IDENTIFY 
AND ASSEMBLE  THE CORRECT ELEMENT SECTIONS. 
 
BEGIN ASSEMBLING THE SMALLEST ELEMENTS FIRST TO ESTABLISH A “ROUTINE” 

 

REFER TO THE ELEMENT 4 THOUGH 11 ASSEMBLY SHEET 

1.  Locate five (5) 7/8 x 30” FIBERGLASS RODS and (10) POLY DISCS with 7/8” holes. Press a 

disc onto the end of a rod and slide it down until it is about 3/4” inside the INNER two 1/4” holes. 
Then slide another poly disc on from the other end of the rod and position it about 3/4” inside the 
other 1/4” hole. Repeat this for all five of the 7/8” FIBERGLASS RODS. Slight repositioning of the 
poly discs may be required when the element is mounted below the boom. 

 

ELEMENT #11 (Smallest) 

2.  Install a PHASE LINE CLAMP with 1” hole at the butt of the 1” x 60.75” element half with the two 

grooves facing the butt. Secure the clamp block temporarily using an 8-32 x 1-1/2” screw and 
locknut. Add a PHASING LINE CLAMP CAP to the PHASE LINE CLAMP using a 1/4-20 x 1” flat 
head bolt and locknut, but finger tighten only at this time. Repeat for the other #11 element half. 
Now slide each element half onto a previously prepared 7/8” FIBERGLASS ROD and align the 
holes. Secure with 1/4-20 x 1-1/2" bolt and locknut. Finally, align the grooved side of the clamp 
block assembly on each side with the NUT SIDE of the bolt holding each element half onto the 
rod. Position the clamp blocks about 1/2” from the end of the element butts and tighten the 8-32 x 
1-1/2” screws and locknuts securing the clamp blocks.  Use a marking pen to identify the element 
as #11. Element #11 is now complete and ready to be installed on the boom at a later time.  

 

ELEMENTS #10, #9, #8,  & #7   

3. These are very similar to #11. Follow the same procedure as in step #2. Follow the ELEMENT 

ASSEMBLY SHEET for the element information and the hardware needed.  Don’t forget  to use 
PENETROX (ZINC) PASTE on all aluminum joints and on the threads of the screws and bolts. 
Element #7 has a 1-1/8” outer sleeve but it still uses a 7/8” FIBERGLASS ROD and a PHASE 
LINE CLAMP with 1” hole for the phasing lines.  

6-30LP11 ASSEMBLY MANUAL 

Summary of Contents for 6-30LP11

Page 1: ...trically Top quality materials combined with many CNC machined parts will keep it trouble free for years or operation Performance is excellent and specific path gain can be as much as 12 dB with groun...

Page 2: ...nd position it about 3 4 inside the other 1 4 hole Repeat this for all five of the 7 8 FIBERGLASS RODS Slight repositioning of the poly discs may be required when the element is mounted below the boom...

Page 3: ...8 OUTSIDE SLEEVE over the butt section to maintain element strength to survive 125 mph winds ELEMENT 4 is unique because at 4 there is transition in phasing line diameter Both PHASE LINE CLAMPS AND 3...

Page 4: ...reign substances that could conduct under the right condition 8 Assembling ELEMENT 2 1 is similar to 3 except ELEMENT 2 1 each use 2 ELEMENT SIDE SUPPORT BRACKETS that are attached to the 2 sections j...

Page 5: ...2 grade 5 galvanized bolts 1 2 13 galvanized nut 1 2 13 galvanized pal nut for all tower boom section joints 2 Shims as shown are supplied with tower sections to help align Use as needed 6 30LP11 BOOM...

Page 6: ...6 30LP11 ELEMENT ASSEMBLY 4 11...

Page 7: ...6 30LP11 ELEMENT ASSEMBLY 3...

Page 8: ...6 30LP11 ELEMENT ASSEMBLY 2...

Page 9: ...6 30LP11 ELEMENT ASSEMBLY 1...

Page 10: ...fiberglass rods and 4 HD CRADLES with 1 1 4 radius Use 5 16 24 x 4 1 2 bolts and locknuts 5 Because of their size and weight we have suggested that just the INNER SECTIONS of element 3 2 and 1 be moun...

Page 11: ...kle eye and over the cable eye Push the cable end back through the clips pull all the slack out of the cable and then push one clip close against the cable eye and begin tightening the nuts on the cli...

Page 12: ...t PHASE LINE CLAMPS only 3 Continue by adding the next set of phasing lines between element 10 and 9 Center align the phasing rods and tighten the PHASE LINE CLAMPS on element 10 Contin ue installing...

Page 13: ...o pairs of 3 8 PHASE LINE CLAMP CAPS on the element butts If not then add them now loosely Continue installing this phase line set using eight 8 3 8 PHASE LINE SUPPORT INSULATORS Center and align the...

Page 14: ...boom itself Slide two 3 8 cable clips on a cable end and route the cable through the turnbuckle over the cable eye and back through the two clips Slide one clip against the cable eye and begin tighte...

Page 15: ...INSULATOR 2 I D 2 CRADLE 2 HD MACH ALUM 8 ELEMENT VERTICAL SUPPORT MAST 1 1 2 X 48 WELDED 1 ELEMENT VERTICAL SUPPORT BRACKET STEEL WELDED 1 ELEMENT SIDE SUPPORT BRACKET ALUMINUM WELDED 2 3 8 PHASE LIN...

Page 16: ...INSULATOR 2 I D 2 CRADLE 2 HD MACH ALUM 4 ELEMENT VERTICAL SUPPORT MAST 1 1 2 X 48 WELDED 1 ELEMENT VERTICAL SUPPORT BRACKET STEEL WELDED 1 ELEMENT SIDE SUPPORT BRACKET WELDED 2 3 8 PHASE LINE CLAMP...

Page 17: ...7 8 X 058 X 71 875 6063 T832 2 ELE 3 SEC 7 3 4 X 049 X 81 SOE 6063 T832 2 ELE 3 SEC 8 1 2 X 049 X 63 6063 T832 2 CENTER SUPPORT INSUL 2 X 36 W COUPLING RINGS 1 POLY DISC INSULATOR 2 I D 2 CRADLE 2 HD...

Page 18: ...T MAST 1 2 X 180 X 96 GALV GUY CABLE HPTG 6700 PHILISTRAN X 70 FT 1 TURNBUCKLE 1 2 X 12 FORGED GALV 2 CRADLE 1 1 2 MACHINED ALUM 13 32 HOLES 16 TOWER SHIM THICK 12 TOWER SHIM THIN 12 HARDWARE BOLT 1 2...

Page 19: ...T6 2 3 16 X ROD BENT 6061 T6 2 PHASE LINE SUPPORT INSULATOR FOR 3 8 TUBE 24 PHASE LINE SUPPORT INSULATOR FOR 3 16 ROD 20 PHASE LINE SUPPORT CAP DELRIN 44 375 PHASE LINE SPACER 3 4 X 2 X 2 DELRIN 3 18...

Page 20: ...1 1 X 058 X 60 SOE 1 4 HOLE 8 ELE 6 SEC 2 1 X 058 X 60 SOE 2 HOLES 2 ELE 4 SEC 4 1 X 058 X 39 SOE 4 SLEEVE 7 8 X 058 X 15 2 ELE 8 SEC 2 3 4 X 049 X 63 STR 2 ELE 9 SEC 2 3 4 X 049 X 39 25 STR 2 ELE 4 S...

Page 21: ...20 X 1 1 2 SS 10 SCREW 1 4 20 X 1 FH SS 16 NUT LOCKING 1 4 20 SS 32 SCREW 8 32 X 2 SS 10 SCREW 8 32 X 1 3 4 SS 10 SCREW 8 32 X 1 1 2 SS 22 SCREW 8 32 X 1 1 4 SS 28 SCREW 8 32 X 1 SS 16 LOCKNUT 8 32 SS...

Page 22: ...6 30LP11 PARTS IDENTIFICATION...

Page 23: ...20 X 2 1 4 SS 4 BOLT 1 4 20 X 2 SS 2 BOLT 1 4 20 X 1 1 2 SS 4 SCREW FLATHEAD 1 4 20 X 1 SS 4 NUT LOCKING 1 4 20 SS 24 SCREW 8 32 X 2 1 4 SS 2 SCREW 8 32 X 2 SS 4 SCREW 8 32 X 1 3 4 SS 4 SCREW 8 32 X...

Reviews: