Required steps
The following procedures have to be observed during assembly
and installation:
Laying the foundation
Installing the empty conduits
Unpacking the pedestrian barrier
Mounting the pedestrian barrier on the foundation
Assemble glass wings and anti-climb panels.
Connect pedestrian barrier electrically, wire modules.
Assemble housing.
7.3
Foundation and empty conduits
Before assembling the pedestrian barrier a foundation has to be
laid and empty conduits have to be installed.
NOTE!
To provide a trouble-free operation use separate
conduits for data cables and mains cables.
Foundation
The foundation must meet the following requirements:
have sufficient load-carrying capacity.
have a skid-proof surface.
be level and horizontal
have sufficient thickness for the fastenings.
Empty conduits
Observe the following during planning and installing of the empty
conduits:
Install empty conduits according to the foundation plan. Refer to
Page 20,
Fehler! Verweisquelle konnte nicht gefunden
werden.
.
Install 2 conduits between each module.
Install a conduit for each module with master function for the
mains cables.
Additional cabling for access control and other peripheral
equipment is the customer’s responsibility.