Pedestrian Pivot Barrier
MPP-112 / MPP-122 / MPP-132 / MPP-212 / MPP-222
Assembly and installation
5817,0016EN / Version 00
33
7.3 Foundation and empty conduits
Before assembling the pedestrian barrier a foundation has to be
laid and empty conduits have to be installed.
NOTE!
To provide a trouble-free operation use separate
conduits for data cables and mains cables.
Foundation
The foundation must meet the following requirements:
have sufficient load-carrying capacity.
have a skid-proof surface.
be level and horizontal
have sufficient thickness for the fastenings.
Empty conduits
Observe the following during planning and installing of the empty
conduits:
Install empty conduits according to the foundation plan.
MPP-112, MPP-132 and MPP-212:
MPP-122 and MPP-222:
Additional cabling for access control and other peripheral
equipment is the customer’s responsibility.
Conduits have to be planned to a sufficient length.