Full Height Turnstile MPT-152
Start-up and operation
52
8.2 Start-up
Inspection prior to initial start-up
The following inspections must be performed prior to initial start-up:
Check power supply.
Check wiring emergency input IN1.
Refer to Page 43, Fig. 30.
Check connection of digital inputs IN2 and IN3.
Refer to Page 43, Fig. 30.
Check connection of relays outputs 1 to 6.
Refer to Page 43, Fig. 30.
Check all screwed connections.
Check pedestrian barrier for ease of movement.
NOTE!
Make sure that, when the power supply is switched
on, there are no obstructions to operation of the
barrier. The access lane must be clear.
Home position setting, see Page 39, Chapter 5.4.9.
8.2.1
Switching on and off the pedestrian barrier
Switching on
Activate main switch on the rear panel of the support beam.
See also Page 41, Fig. 28.
Switching off
Deactivate main switch on the rear panel of the support beam.
See also Page 41, Fig. 28.
NOTE!
Wait at least 10 seconds between switching off and
restoring the power supply.