Full Height Turnstile MPT-152
Assembly and installation
24
5.2 Requirements for assembly
The following procedures have to be observed before assembly
and installation:
Laying the foundation
Installing the empty conduits
5.3 Foundation and empty conduits
NOTE!
To provide a trouble-free operation use separate
conduits for data cables and mains cables.
The functional safety of the pedestrian barrier
hinges on the accuracy of the foundation.
Foundation
The foundation must meet the following requirements:
have sufficient load-carrying capacity.
have a skid-proof surface.
be horizontal and level, max. deviations 2 mm/m
have sufficient thickness for the fastenings.
Empty conduits
The empty conduits must be positioned accurately to the drilling
plan. Refer to page 25, Fig. 2.