Full Height Turnstile MPT-152
Assembly and installation
25
5.3.1 Foundation
plan
Fig. 2: Foundation plan
Have cables overlapping for approx. 5 m of the conduits
Composite anchors M10
Bore hole diameter 16 mm, drilling depth 90 mm
Conduit for mains cable and data line
Foundation level and horizontal
Concrete or adequately integrated industrial flooring
With flagging, it is important to ensure that the anchor bolts grip
firmly into the foundation, use longer bolts if necessary.