33
mTripod
Installation and assembly
7.4
Setting up foundation and placing empty conduits
7.4.1
Requirements foundation
The foundation must meet the following requirements:
›
Have sufficient load-carrying capacity
›
Concrete C20/25 or corresponding industrial floor
›
Attachment must be able to grip securely
›
Foundation cross section according to foundation and empty conduit plan
›
Non-slip surface
›
Horizontal and level.
ä
Foundation and empty conduit plan mTripod FMTP-ML: Page 35, Fig. 6.
ä
Foundation and empty conduit plan mTripod FMTP-MS: Page 37, Fig. 8.
For outdoor assembly, the foundation must meet the following additional
requirements:
›
Concrete C35/45 XD 3 XF2
›
Foundation depth: at least 800 mm, frost-proof. Adjust foundation depth to
the local conditions.
›
Reinforcement mesh according to reinforcement plan
ä
Reinforcement plan mTripod FMTP-ML: Page 36, Fig. 7.
ä
Reinforcement plan mTripod FMTP-MS: Page 38, Fig. 9.
7.4.2
Requirements empty conduits
Observe the following points for the empty conduits:
›
Place empty conduits according to the foundation plan.
›
Conduits have to be planned to a sufficient length.
›
Plan empty conduits required for access-control devices and other
peripheral devices. The cabling for this is the responsibility of the customer.
IMPORTANT!
To ensure trouble-free operation, separate empty conduits must
be installed for all mains cables and control lines.