6 Installation
8
off protruding construction foam and shims
flush with the masonry block.
ATTENTION:
Note the gradient. Building dam-
age due to condensation if installed incorrectly.
Information on PP 45 and PPB 30 units
•
PP 45:
Use the recess shown in the figure to
feed the connection cable. This is positioned in
the
PP 45
unit to match the line feedthrough.
•
PPB-30:
Feed the connection cable outside the
masonry block.
6.2 Installation of PP 45 RS
PP 45 RS: Minimum distances to the wall and
ceiling
Projection of the wall sleeve (on delivery) for
internal and external covers
• inside 12 mm
• outside 40 mm
Minimum distances for PP 45 units
Minimum distances for PPB 30 units
Shortening the PP 45 RS
1. Shorten the
PP 45 RS
on the outside
in the
area between the cutting marks to the appro-
priate size. Use a saw suitable for EPS. Ob-
serve the markings for the wall thicknesses
Only saw PP 45 RS carefully, all the way
round to the wall sleeve! Do not saw the wall
sleeve. Remove sawn-off EPS polystyrene
parts.
Shorten wall sleeve.
1. Shorten and deburr the wall sleeve according
to the wall thickness. Take into account the re-
quired wall sleeve projections for plaster, ma-
sonry, internal and external cover.
Wall sleeve projections
•
Shorten
the wall sleeve
on the outside
. Ob-
serve the
prescribed
wall sleeve projection for
the respective external cover.
Summary of Contents for PP 45 RS