background image

9

GBR Series B-Vent Gas Fireplace

7412955

EB-1 Electrical Box

The fireplace, when installed, must be elec-
trically connected and grounded in accor-
dance with local codes or, in the absence 
of local codes, with the current CSA C22.1 
Canadian Electrical Code. 

For USA installations, follow local codes 
and the National Electrical Code, ANSI/
NFPA No. 70.
It is strongly suggested that the wiring of 
the EB-1 electrical junction box be carried 
out by a licensed electrician.
Ensure that the power to the supply line 
has been disconnected before commenc-
ing this procedure.

Once the fireplace is secured, complete wiring the fan 
kit. Remove knockout in the center of the back of the 
EB1 and install listed cable clamps. Feed electrical 
wire through cable clamp leaving approximately six (6) 
inches of wire exposed through the EB1. Secure cable 
clamp to the wire.
Attach white wire from power source to one (1) wire of 
receptacle and secure with a nut. Attach black wire from 
power source to the other wire of the receptacle and 
secure with a nut. Be sure nuts are tightened securely.
Secure the EB1 assembly to the inside of the electrical 
box coverplate using two (2) screws. Attach the cover 
to the face of the EB1 while being careful to position 
excess wire completely within the EB1. Attach the cov-
erplate to the fireplace. (Fig. 8)

FP580
INSTA VENT FREE
EB1 JUNCTION BOX
11/18/97

Outside

Electrical Box

Front Of Unit

Inside

Front Of Unit

FP580

Fig. 8

  Junction box (EB-1) hook-up.

 Install the Venting System, 

Flashing and Termination

See venting installation instructions provided by the B-
Vent manufacturer.  
Refer to Page 4, Figure 1 to locate chimney centerline 
dimension from a combustible back wall.

• Minimum vertical chimney height — 12 feet (3.65m).
• Maximum vertical height — 40 feet (12m).
• Minimum height with two 90° elbows — 16 feet 
(4.06m)
• Elbow requirements allow a maximum of two
90 degree elbows or four 45 degree elbows
per installation. (Two 45 degree elbows =    
One 90 degree elbow.) See venting chart for
proper elbow offset runs. Use Figure 10 for GBR36 
installations when not installing the GSKBB Single 
Panel Glass Door. Use Figure 11 for GBR36  instal-
lations when installing the GSKBB Single Panel 
Glass Door.

For firestop positioning, refer to Figure 9. Only one (1) 
firestop required per frame. 

NOTE:

 A firestop is not 

required at the roof.

Fig. 9

  Firestop/draftstop positions.

Ceiling Installation

FP384 

FIRESTOP

11/21/96

adapted from IGF53

Attic Installation

Firestop position when area above ceiling is an attic.

Firestop position when area above ceiling is NOT an attic.

(Firestop/draftstop 

appearances may 

vary. Only 1 firestop 

required per frame.)

Firestop

Spacer

Nails (4)

Joist

FP384

Summary of Contents for GBR36 Series

Page 1: ...life FOR YOUR SAFETY Installation and service must be performed by a quali ed installer service agency or the gas supplier Do not store or use gasoline or other am mable vapors and liquids in the vici...

Page 2: ...bustibles 5 Mantels 5 Mantel Chart 5 Hearth 5 Framing Finishing 6 Final Finishing 6 Gas Speci cations 6 Gas Inlet Manifold Pressures 6 High Elevations 6 Parts Identi cation and Chase Installation 7 Ga...

Page 3: ...on air must not be obstructed in any way 11 Whether the appliance is installed directly on carpeting vinyl tile or any combustible material other than wood this appli ance must be installed on a metal...

Page 4: ...1016mm 36 914mm 3 76mm 1 6 m m 37 953mm 13mm 5 4 1 3 7 2 m m 19 502mm 21 533mm 40 1029mm 7 191mm 6 165mm 7 191mm 7 191mm Outside Air Electrical Access Gas Line Access WFP623 GBR36 2 11 98 Rough Openin...

Page 5: ...70 DV Builder Front View O N M L K J F G H I Mantel Leg CFM164a Mantel Leg Chart 06 22 01 sta Black Surround Face Side of Combustion Chamber CFM170 CFM164 Hearth Extension A hearth extension in front...

Page 6: ...struct or modify the air inlet outlet grilles in any manner Finish the wall with the material of your choice Refer to Figures 2a and 2b for speci c clearances when install ing a combustible mantel or...

Page 7: ...essure equal to or less than 1 2 psig 3 45 kPa The appliance and its individual shutoff valve must be disconnected from the gas supply piping system during any pressure testing of that system at test...

Page 8: ...to a conveniently located wall receptacle box 2 Attach wire to switch and install switch into recep tacle box Attach cover plate to switch 3 Connect wiring to gas valve Refer to Figure 6 or 7 dependin...

Page 9: ...ion excess wire completely within the EB1 Attach the cov erplate to the replace Fig 8 FP580 INSTA VENT FREE EB1 JUNCTION BOX 11 18 97 Outside Electrical Box Front Of Unit Inside Front Of Unit FP580 Fi...

Page 10: ...ed within the vent system using a maximum of two 45 degree elbows B FP567a Fig 11 Venting con gurations when installing 36GSKBB FP567 Fig 10 Venting con gurations FP567 NVBR NVBC VENTING RUNS 11 12 97...

Page 11: ...hold cleaner and warm water we recommend gas replace glass cleaner After that the glass should be cleaned two or three times during each heating season depending on the circumstances present Clean gla...

Page 12: ...on gas valve standing pilot only FP390 LO H I Turn counterclockwise to increase flame height Turn clockwise to lower flame height FP390 FLAME ADJUSTMENT KNOB 11 21 96 Flame Characteristics It is impor...

Page 13: ...smell all around the heater area for gas Be sure to smell next to the oor because some gas is heavier than air and will settle on the oor WHAT TO DO IF YOU SMELL GAS Do not try to light any replace D...

Page 14: ...d to push in or turn the gas control knob Never use tools If the knob will not push in or turn by hand do not try to repair it call a quali ed service technician Force or attempting repair may result...

Page 15: ...eded All wiring connections Replace Piezo Ignitor Thermodisk For Air in the lines Thermopile needs a minimum 325mV Adjust pilot flame height All wiring connections Replace Thermopile Thermocouple need...

Page 16: ...ight All Wiring connections Replace thermopile Thermocouple needs a minimum 14mV Defective valve Turn to pilot meter should read greater than 100mV If not replace Thermodisk Pilot Lights with Piezo Ig...

Page 17: ...n cable for signs of melting or buckling Take protective actions to shield cable and boot from excessive temperatures Check for 24VAC across MV MV PV terminals If no voltage replace module Check elect...

Page 18: ...r shutter should be set to 1 16 open 6 Install manifold to burner tube 7 Reinstall burner tube and retaining bracket Burner ori ce and air shutter conversion complete FC102 Air shutter 7 21 99 djt Bur...

Page 19: ...ube enters the pilot as sembly Tighten tting if necessary 3 Light the main burner and check for leaks around the new pressure regulator assembly Tighten screws if necessary 4 With the main burner ON c...

Page 20: ...y a quali ed technician In order to properly clean the burner and pilot assem bly turn off the gas to the unit open the glass door if used remove logs exposing the burner and pilot assembly Clean all...

Page 21: ...es the right to make changes in design materials speci cations prices and discontinue colors and products at any time without notice GBR36 Ref Description GBR36 1 Log Set Assembly 20005291 1a Back Log...

Page 22: ...37 17 Door Track 3061104 18 Remote Switch Kit 53875 19 Lava Rock Package 55255 20 Bag of Embers 7060109 21 Valve Cover 3078116 22a Electronic Valve Natural 57884 22b Electronic Valve LP 57883 23a Elec...

Page 23: ...e appliance model number 2 The serial number 3 A description of the part Should you need additional information beyond what your dealer can furnish contact CFM Specialty Home Products 410 Admiral Blvd...

Page 24: ...Optional remote control units are available to control different functions of the appliance Model Function s Controlled MRC1 ON OFF MRC2 ON OFF and Temperature MRC3 ON OFF and Temperature control with...

Page 25: ...25 GBR Series B Vent Gas Fireplace 7412955...

Page 26: ...26 GBR Series B Vent Gas Fireplace 7412955...

Page 27: ...f upon inspection the damage is found to be the fault of the manufacturer repairs will be authorized at no charge to the customer parts and or labor Any part and or component replaced under the provis...

Page 28: ...410 Admiral Blvd Mississauga Ontario Canada L5T 2N6 905 670 7777 www majesticproducts com www vermontcastings com CFM Specialty Home Products...

Reviews: