04_20ed3a Pre Delivery Prep.fm
4 - 9
3UH,QVWDOODWLRQ*XLGH
('*(
4.3.4
Foundation
A reinforced, isolated, concrete floor is the best foundation to minimize
vibration and deflection (see
for detail on foundations, floorplans,
and dimensional drawings).
•
The concrete pad should be continuous, flat, and strong enough to
support the weight of the machine without appreciable deflection.
•
Do NOT place machine on separate sections of concrete.
As a rule of thumb, the foundation must meet the following specifications:
•
Minimum ground resistance of 5 Ton/M
2
•
Minimum foundation thickness of 300mm
•
Foundation should extend 300mm beyond the machine base.
•
Level within 3.2mm/m
If the floor does not meet these specifications, a special foundation is
needed to maintain machine level and alignment. If you are considering a
special foundation, contact Makino.
When locating the machine on an upper floor of a building, be sure to:
•
Consult a structural engineer for load bearing capacity.
•
Consult Makino for acceptance or stipulations on this arrangement.
4.4
Fixtures
Fixtures typically require a long lead time. Address this issue before the
delivery of the machine tool.
Consider design and manufacturing time, and coordinate completion with
the delivery of the machine for a smooth transition into your production
schedule.
To ensure machine accuracy and performance, customers must comply with all installa-
tion and foundation requirements. Failure to comply may void the accuracy portion of
the warranty. Consistent accuracy can only be guaranteed on a reinforced concrete
foundation that meets the minimum specifications for the machine.
Summary of Contents for EDGE-2
Page 8: ...vi 3UH QVWDOODWLRQ XLGH...
Page 11: ...01_20ed3aSafety fm 3UH QVWDOODWLRQ XLGH 1 11 Installation Safety Instructions 1 25...
Page 12: ...3UH QVWDOODWLRQ XLGH NOTES SKETCHES...
Page 34: ...1 22 3UH QVWDOODWLRQ XLGH FIGURE 1 4 OILMATIC SAFETY LABELS...
Page 38: ...1 26 3UH QVWDOODWLRQ XLGH NOTES SKETCHES...
Page 63: ...02_20ed3a Specifications fm 2 23 3UH QVWDOODWLRQ XLGH NOTES SKETCHES...
Page 64: ...2 24 3UH QVWDOODWLRQ XLGH...
Page 74: ...3 8 3UH QVWDOODWLRQ XLGH NOTES SKETCHES...
Page 79: ...04_20ed3a Pre Delivery Prep fm 4 3 3UH QVWDOODWLRQ XLGH NOTES SKETCHES...
Page 87: ...04_20ed3a Pre Delivery Prep fm 4 11 3UH QVWDOODWLRQ XLGH NOTES SKETCHES...
Page 88: ...4 12 3UH QVWDOODWLRQ XLGH NOTES SKETCHES...
Page 103: ...05_20ed3a Machine Delivery fm 5 13 3UH QVWDOODWLRQ XLGH NOTES SKETCHES...
Page 104: ...5 14 3UH QVWDOODWLRQ XLGH NOTES SKETCHES...
Page 112: ...SSHQGL A 6 NOTES SKETCHES...
Page 120: ...SSHQGL A 14 NOTES SKETCHES...