PRE-INSTALLATION GUIDE : METAL X SYSTEM
SINTER-1
ELECTRICAL SETUP
Before the Installer can complete the Sinter-1
installation, you must work with a licensed
electrician to connect the dedicated power
supply to the Sinter-1 unit. The facility electrical
supply should already meet the specifications
in the
Facilities Guide
.
1. Remove the panel on the inlet (left-hand)
side of the unit.
2. After feeding through the conduit entry, line
1 connects to the left grey terminal block,
line 2/Neutral to the right grey terminal
block, and ground to the green/yellow
block according to these specifications:
EQUIPMENT GROUNDING TERMINAL
●
Copper conductors only. 10AWG - 4AWG
●
5.5mm flat head screwdriver
●
torque to 1.4 N-m (12 in-lb)
PHASE CONDUCTOR TERMINAL
●
Copper conductors only. 6AWG - 2AWG
●
4mm Allen hex drive
●
torque to 5.1 N-m (45 in-lb)
STOP HERE.
At this point you should contact your Installer to schedule the complete system
installation. If you have completed all the steps in this guide, you have fulfilled your
pre-installation responsibilities. The Installer will use the checklist on the following
pages to determine whether your site fully complies with all facility requirements
and is prepared for final system installation, configuration, and setup.