CHANGING GEAREDUCER OIL

Drain the Geareducer oil by removing the drain plug. See 

Figure 

for location. If equipped with an external dipstick/oil level gauge, 

remove the drain plug at that location, and drain the entire system.
To maximize service life of the Geareducer, remove a sample from the 
drained oil and look for evidence of foreign material, such as water, 
metal shavings or sludge, or send the oil sample to an oil analysis 
lab for inspection. If you find unacceptable condensation or sludge, 
flush the Geareducer with mineral oil before refilling. 
After inspection is complete, fill the Geareducer with 

53 liters

 of 

oil. See 

Figure 1

 for location. If the Geareducer is equipped with 

an external dipstick/oil level gauge an additional 3 to 4 liters of oil 
will be required. Be certain that the vent on the Geareducer (and 
external dipstick/oil level gauge, if present) is not plugged. Verify 
that the gauge/drain line is full and that there aren't any leaks at 
the connections.

Alternate procedure:
If the cooling tower has an external oil gauge and drain line equipped 
with a three-way valve below the oil level gauge. See 

Figure 2

.

1.  Remove pipe plug. Turn valve control stem clockwise to open 

drain.

2.  With Geareducer drained, the three-way valve turned clockwise, 

and the pipe plug removed, connect fill source (usually a hose 
to a pump, to the three-way valve).

operation and service

 

Pump oil through the hose. Check oil level occasionally by 
turning the valve control stem counterclockwise and allowing 
the oil level in the sight glass to stabilize. Continue filling until 
full level mark is reached.

3.  With the oil level at the full mark turn the valve control stem 

counterclockwise to close the drain and open the valve to the 
sight glass. Remove the oil filling line and reinstall pipe plug in 
the three-way valve.

REPAIR AND OVERHAUL

The Model 2700 and 3000 Geareducer is assembled using special-
ized tools and fixtures. Bearings and gear sets are unique and not 
available from other sources. Geareducers can be repaired in the 
field — however, major repairs require the use of a fully equipped 
machine shop. Refer to the 

Field Repair

 section of this manual for 

further instructions.
If your Geareducer ever needs replacement or repair, Marley recom-
mends returning the unit to a Marley factory service center. Contact 
your Marley sales representative to discuss course of action. A factory 
reconditioned Geareducer carries a one year warranty. The Marley 
Order Number on your cooling tower will be required if the Geareducer 
is shipped back to the factory for repair. Obtain a 

“Customer Return 

Material”

 tag from the Marley sales representative in you area. 

To find your Marley sales representative call check the internet at 
spxcooling.com/sales.

OIL LEVEL CHECK

OIL GAUGE

AND DRAIN LINE

OIL GAUGE

VENT

OIL LEVEL

GAUGE

DRAIN PLUG

THREE-WAY

VALVE

Figure 2 – Service Fittings

Summary of Contents for 2700-3000 Series

Page 1: ...2700 3000 Series Geareducer INSTALLATION OPERATION MAINTENANCE user manual uk_Z0529732_A ISSUED 06 2017 READ AND UNDERSTAND THIS MANUAL PRIOR TO OPERATING OR SERVICING THIS PRODUCT ...

Page 2: ...ng alignment x Inspect and tighten driveshaft or coupling fasteners x Check driveshaft or coupling bushing flex elements for unusual wear x Lube Lines if equipped Check for oil leaks in hoses and fittings x R x R Refer to instructions within this manual Note It is recommended at least weekly that the general operation and condition be observed Pay particular attention to any changes in sound or vi...

Page 3: ...s Geareducers supplied with new towers include oil for the initial fill ing Oil is not furnished with Geareducers supplied as spares or on replacement orders Before operating the mechanical equipment check to be sure the oil level is at the full mark at the Geareducer and that the external gauge placard if equipped full mark corre sponds with the Full level in the Geareducer Check any oil lines to...

Page 4: ...k mechanical equipment anchor bolts drive shaft coupling bolts and coupling set screws Tighten as required Check Geareducer exterior yearly and touch up with epoxy paint if required Coat all exposed threads at pipe joints to prevent corrosion Every 5 Years If using Marley synthetic Gearlube change oil To maintain five year change intervals use only Marley Gearlube It is recommended to monitor the ...

Page 5: ...to a pump to the three way valve operation and service Pump oil through the hose Check oil level occasionally by turning the valve control stem counterclockwise and allowing the oil level in the sight glass to stabilize Continue filling until full level mark is reached 3 With the oil level at the full mark turn the valve control stem counterclockwise to close the drain and open the valve to the si...

Page 6: ...list 210 502 BEARING RETAINER 203 202 101 301 420 104 105 103 311 503 312 501 PINION CAGE PINION CAGE CAP 320 DOWEL PIN 420 412 201 102 101 008 VENT WATER SLINGER GEAREDUCER CASE 204 411 BOTTOM CAP CASE COVER DOWEL PIN ...

Page 7: ...4 Tongue Washer 105 Lockwasher 200 Fan Shaft Set 201 Fan Shaft 202 Ring gear hub key 203 Fan key 204 Ring spacer Model 2700 Geareducer only 210 Fan attaching hardware Cap screws and washers 301 Oil Slinger 310 Set of Two Pinion Shaft Bearings 311 Head tapered roller bearing 312 Tail tapered roller bearing 320 Pinion Cage Shims 410 Fan Shaft Bearing Set 411 Lower tapered roller bearing 412 Upper ta...

Page 8: ... ring of bolts in pinion cage and remove pinion subassembly Note The thickness of the shim pack 320 is important in resetting thegears Theshimpackshouldeitherbesavedorcarefullymeasured with a micrometer If the gears are to be replaced record the pinion setting distance that is etched on the pinion gear See Figure 4 3 Remove water slinger 4 Remove bearing retainer and shim pack 420 from top of case...

Page 9: ...pinion shaft making sure oil slinger and bearing are against gear 3 Press bearing cups 311 and 312 into pinion cage 4 Lower pinion cage on pinion shaft until head bearing cone and cup mate 5 Press tail bearing cone 312 on pinion shaft until it mates with its bearing cup 6 Install locknut lockwasher and tongue washer 103 105 and 104 Tighten nuts on bearing cone until 8 to 12 in lbƒ 904 1356 mN m of...

Page 10: ...nthebacklashetchedonthegearset findtheequivalent backlash setting in Table 2 Column 2 2 With the X marked tooth on the pinion gear engaged be tween the two X marked teeth on the ring gear check the backlash with a dial indicator as shown in Figure 5 Lock the pinion shaft against rotation The amount of movement of the fan shaft measured at a distance equal to the outside radius of the ring gear is ...

Page 11: ...11 field repair Table 2 Backlash Etched on Gears Set the Gears to Backlash 008 010 003 008 009 0115 003 008 010 013 003 008 011 014 004 010 012 015 004 010 013 017 004 010 014 0185 004 010 ...

Page 12: ...ION In the interest of technological progress all products are subject to design and or material change without notice SPX COOLING TECHNOLOGIES UK LTD 3 KNIGHTSBRIDGE PARK WORCESTER WR4 9FA UK 44 1905 750 270 ct fap emea spx com spxcooling com Geareducer US E R MAN UAL ...

Reviews: