© Martin Engineering GmbH
14
M3814UK-03/16
Installation
5.2
Installation procedure
5.2.1
Determining the installation position
The position of the mainframe and the tensioner of the MARTIN
®
(PD) QC
™
#1 HD MT primary cleaner must be determined on both
sides of the chute wall. In doing so, the positions are determined
where the mainframe of the MARTIN
®
(PD) QC
™
#1 HD MT primary
cleaner passes through the chute wall or where the tensioner is in-
stalled on the chute wall.
The MARTIN
®
(PD) QC
™
#1 HD MT primary cleaner is operated in
conjunction with a tensioner. This is de-installed at the factory before
delivery and is reinstalled during the installation along with the pri-
mary cleaner.
The installation of the MARTIN
®
(PD) QC
™
#1 HD MT primary clean-
er and the tensioner is described in this manual and the installation
manual of the tensioner.
There follows an overview of the installation steps:
It is possible to have different local conditions at the time of installa-
tion; these require different working steps, which are illustrated be-
low:
Installation on an encapsulated delivery system
•
Carry out the instructions according to chapter 5.2.2
onwards.
Installation on an encapsulated delivery system with existing instal-
lation openings and brackets for belt cleaners.
•
Carry out the instructions given in chapter 5.2.3 onwards.
Installation on an open delivery system
•
Use the local resources to ensure that the dimensions for
the installation are correctly maintained.
No.
Installation step
Instruction
1
Determining the installation position
M3814
2
Installing the primary cleaner
M3814
3
Installing the tensioner
Tensioner
4
Installing the scraper
Tensioner
Tab. 1: Installation steps