Installation
4. Determine or measure the radius (measurement A) of the driv-
ing drum including the thickness of the covering and the con-
veyor belt.
5. Add measurement X from table 2 to measurement A.
6. On the chute wall, mark a circular arc around the midpoint with
the measurement determined in step 5 (1, Fig.1).
7. Mark a horizontal line below the horizontal centre line of the
head drum at a distance of 355 mm. The intersection with the
arc marked in step 5 is the midpoint of the mainframe (3, Fig.2).
Diameter of the drum* in mm
Measurement X in
mm
400
146
500
140
600
133
700
127
750 - 3000
120
*incl. Friction material and conveyor belt
Tab. 2: X values for the positioning of the blade shaft
Fig. 2: Marking the installation height
WARNING! DANGER OF INJURY!
The primary cleaner is heavy and can cause serious injury if it falls
when being lifted or moved.
Only lift the secondary cleaner using suitable lifting device or with
several persons. Do not stand under suspended loads.
3
90°
355
90°
mm