1 Installation and location of the unit
The equipment must be installed and commissioned by an authorized, specialized installation
company. The installation must comply with this installation manual and national regulations.
1.1 Unit delivery
Check the unit for possible damage or missing parts. Should you find any damage, or should
the delivery not be complete, immediately contact the supplier’s forwarder or the manufacturer
directly.
1.2 Handling instructions
Handle the unit in accordance with the presented drawings. Using other handling methods may
damage the unit.
1.3 Location of the indoor unit
1.3.1 Working environment and clearances
Indoor units are dedicated for indoor installation in dry, non explosive and non corrosive
environment at temperatures +5÷+30˚C without free public access. There must be a sufficient
clearance around the unit for the antifreeze, heating water, refrigerant and electric connections.
Minimal clearance for different unit please see on pictures below.
* Obligatory for units with passive cooling.
400mm recommended for standard units.
It is possible to fully integrate standard
units. Service is possible from the front
and top sides for the standard units.
Clearances: AirMaster AKU, AQxxIC