50
When re-installing your SolarBee, please
carefully read and follow the instructions in this
section.
TOOLS / EQUIPMENT REQUIRED:
• Small Boat with 3+ HP Motor
• 25 ft (7.5 m) Tow Strap/Rope
• Crane, Back Hoe, or other equipment
capable of reaching out into the water and
hoisting 2000 lb (900 kg).
• 3 point lifting chain/strap, 2000 lb (900 kg)
capacity.
• Metric Socket and Wrench Set (Sizes 10mm,
13mm and 19mm Required)
• Pliers
SolarBee Installation
Hoisting SolarBee Out Of Water
Towing SolarBee Using Small Boat
Staging Area With Disassembled SolarBee Units
JOB OUTLINE:
1) Locate Staging and Deployment Area
2) Assembly of Major Components
3) Deploy and Float SolarBee
4) Tow SolarBee Into Final Position
5) Final Settings
JOB PERSONNEL AND DURATION:
Installation of 1 SolarBee unit will require
approximately 4 to 6 hours with 2 to 3 workers.
For large water bodies with long distances to
tow the SolarBee unit, allow for additional time
and favorable weather conditions.