Installation guide solar modules 

 

 

V1 – April 2015 

10 - 19 

 

4.2

 

Installing the module 

Make sure that the installation is carried out safely. 

Protect  yourself  and  other  persons  from  falling,  do  not  carry  out  the  installation  in  heavy  winds  and 

eliminate  the  risk  of  falling  objects  as  much  as  possible.  Secure  the  work  area  in  order  to  avoid  the 

endangerment or injury of persons. 

In order not to exceed the max. System voltage at -10 °C, the MBF-GG60 and MBA-GG60 modules must not 

be connected in series with more than 22 modules. 

Additionally, the requirements of the inverters must be observed. In any case, specific checking have to be 

done by the designer, considering the modules working temperatures.  

4.3

 

Observe the allowable maximum mechanical loading: 

Do not exceed the maximum mechanical loading and avoid local pressure. Make sure to consider location-

specific  loads  such  as  wind  or  snow.  Remember  that  the  module  might  sag  when  loaded  under  certain 

circumstances.  In  order  to  avoid  damaging  the  module  by  pointed  or  uneven  structures,  do  not  place 

fasteners or cable ties between the rear of the module and the cross section. 

 

4.4

 

Make sure that the surroundings are suitable: 

Make  sure  that  after  installation  the  module  is  neither  subjected  to  artificially  concentrated  sunlight, 

immersed in water or continuously splashed with liquids. By all means make sure that the module is not 

subjected  to  abnormal chemical  exposure.  Exposing  the  module  to  extreme  levels  of  salt  or sulphur  may 

lead to corrosion

 

4.5

 

The correct location for installation: 

 Beside  the  module  itself,  the  mounting  system  must  also  be  suited  to  the  expected  conditions  at  the 

location of installation (snow, wind) and withstand them easily. The bottom side of the module frame (if 

present)  features  holes  for  draining  precipitation  water.  Make  sure  during  installation  that  these  holes 

retain their function. For portrait mounting, the junction box may be mounted facing up or down on the 

underside of the module but it’s preferable to be mounted facing upwards on the underside of the module. 

 

4.6

 

Yield maintenance through optimal alignment and inclination: 

We advise you to familiarize yourself with the appropriate alignment and inclination of the modules prior 

to  installation  in  order  to  ensure  an  optimal  system  yield.  The  ideal  conditions  for  the  generation  of 

electricity are accomplished when the sun rays reach the generator surface perpendicularly. For modules 

connected in a series, make sure that all modules have the same alignment and inclination in order to avoid 

performance losses. 

 

Summary of Contents for MBA-GG60 BiSoN Series

Page 1: ...Document name MCELL_PV_Modules_Installation_Manual_EN_v1 2_20150715 Revision date V1 2 July 2015 www megacell it SAFETY AND INSTALLATION MANUAL BIFACIAL SOLAR MODULES...

Page 2: ......

Page 3: ...allowable maximum mechanical loading 10 4 4 Make sure that the surroundings are suitable 10 4 5 The correct location for installation 10 4 6 Yield maintenance through optimal alignment and inclination...

Page 4: ...Installation guide solar modules V1 April 2015 4 19...

Page 5: ...Installation guide solar modules V1 April 2015 5 19 1 MODULES 1 1 MBF GG60 BiSoN series with frame 1 2 MBA GG60 BiSoN series frameless...

Page 6: ...oduct are beyond company control MegaCell does not assume responsibility and expressly disclaims liability for loss damage or expense resulting from improper installation handling or use The informati...

Page 7: ...d after installation to calculate correctly inverter cables and connection size Serial number Each individual module is identified by a unique serial number accompanied with a barcode They are permane...

Page 8: ...r modules generate electricity When exposed to light a voltage occurs which can be dangerous and life threatening Even though the individual modules generate a relatively low voltage of 50 V DC the vo...

Page 9: ...and safe unpacking Please refers to the instructions printed on the cartoon box of each pallet The modules are sensitive technical components which must be handled with utmost care Therefore be partic...

Page 10: ...re that after installation the module is neither subjected to artificially concentrated sunlight immersed in water or continuously splashed with liquids By all means make sure that the module is not s...

Page 11: ...f the module frame if present is not required for fault free operation To reduce the risk of electric shock e g due to static charge as far as possible MegaCell recommends to ask an experienced instal...

Page 12: ...ith the frame Then turn the screw another quarter or half turn The thread cutting screw should be torqued by 20 4 lb in and 24 8 lb in 2 3 and 2 8 Nm Ground wire placement Insert the cable into the wi...

Page 13: ...hould not be mounted in such a way that the drain holes of the module can become blocked MegaCell PV modules are suitable for mechanical mounting both in portrait and landscape orientation In choosing...

Page 14: ...will render the product and performance warranty void 5 2 Frameless modules The use of frameless MegaCell modules requires frameless mounting system that grabs the edge of the module with a pressure...

Page 15: ...snow load zones the terrain category and the height of the building 6 ELECTRICAL INSTALLATION Do not connect or disconnect modules under load Danger Risk of serious injury or death from electric shock...

Page 16: ...ed against reverse polarity o Keep the total area of all conductor loops as low as possible in order to reduce the voltages due to indirect lightning strikes o Always carry out a careful final check o...

Page 17: ...LES MegaCell recommends to inspect the installation on a regular basis with following minimum maintenance o Check the electrical and mechanical connections to verify that they are clean secure and und...

Page 18: ...sual appearance of the module surface and result in decreased performance o Use of automatic cleaning machines for solar energy systems is at your own risk and is not authorized by MegaCell in any way...

Page 19: ...Document name MCELL_PV_Modules_Installation_Manual_EN_v1 2_20150715 Revision date V1 2 July 2015 www megacell it MegaCell S r l a socio unico A coordinated company part of Mega Group S r l Registered...