Installation guide solar modules 

 

 

V1 – April 2015 

15 - 19 

 

o

 

Firmly  clamp  and  hold  the  entire  perimeter  of  the  module,  on  both  the  front  and  back  of  the 

module.  

o

 

The module shall be fully supported by at least 10mm from the edge on all sides of the module.  

o

 

Any shading or covering of the cells on both sides in the module must be avoided  

 

5.4

 

Clamping areas and maximum load applicable      

                

   

       

 

 

 

Note: 

Pay  attention  to  the  maximum  load-bearing  capacity  of  the  modules,  with  consideration  of  wind  and  snow 

load zones, the terrain category and the height of the building. 

 

6.

 

ELECTRICAL INSTALLATION 

Do  not  connect  or  disconnect  modules  under  load! Danger!  Risk  of  serious  injury  or  death  from  electric 

shock or electric arc flash. 

 

The solar modules are designed for use in PV systems of application class A and are approved for operation 

in systems with dangerous direct current (more than 120 V DC in accordance with EN 61730) and power. PV 

modules of this application class are approved for operation in installations with unrestricted access.  

BiSon series modules from MegaCell, which are qualified under EN 61730 and have been properly installed, 

meet the requirements of protection class II. 

 

Summary of Contents for MBA-GG60 BiSoN Series

Page 1: ...Document name MCELL_PV_Modules_Installation_Manual_EN_v1 2_20150715 Revision date V1 2 July 2015 www megacell it SAFETY AND INSTALLATION MANUAL BIFACIAL SOLAR MODULES...

Page 2: ......

Page 3: ...allowable maximum mechanical loading 10 4 4 Make sure that the surroundings are suitable 10 4 5 The correct location for installation 10 4 6 Yield maintenance through optimal alignment and inclination...

Page 4: ...Installation guide solar modules V1 April 2015 4 19...

Page 5: ...Installation guide solar modules V1 April 2015 5 19 1 MODULES 1 1 MBF GG60 BiSoN series with frame 1 2 MBA GG60 BiSoN series frameless...

Page 6: ...oduct are beyond company control MegaCell does not assume responsibility and expressly disclaims liability for loss damage or expense resulting from improper installation handling or use The informati...

Page 7: ...d after installation to calculate correctly inverter cables and connection size Serial number Each individual module is identified by a unique serial number accompanied with a barcode They are permane...

Page 8: ...r modules generate electricity When exposed to light a voltage occurs which can be dangerous and life threatening Even though the individual modules generate a relatively low voltage of 50 V DC the vo...

Page 9: ...and safe unpacking Please refers to the instructions printed on the cartoon box of each pallet The modules are sensitive technical components which must be handled with utmost care Therefore be partic...

Page 10: ...re that after installation the module is neither subjected to artificially concentrated sunlight immersed in water or continuously splashed with liquids By all means make sure that the module is not s...

Page 11: ...f the module frame if present is not required for fault free operation To reduce the risk of electric shock e g due to static charge as far as possible MegaCell recommends to ask an experienced instal...

Page 12: ...ith the frame Then turn the screw another quarter or half turn The thread cutting screw should be torqued by 20 4 lb in and 24 8 lb in 2 3 and 2 8 Nm Ground wire placement Insert the cable into the wi...

Page 13: ...hould not be mounted in such a way that the drain holes of the module can become blocked MegaCell PV modules are suitable for mechanical mounting both in portrait and landscape orientation In choosing...

Page 14: ...will render the product and performance warranty void 5 2 Frameless modules The use of frameless MegaCell modules requires frameless mounting system that grabs the edge of the module with a pressure...

Page 15: ...snow load zones the terrain category and the height of the building 6 ELECTRICAL INSTALLATION Do not connect or disconnect modules under load Danger Risk of serious injury or death from electric shock...

Page 16: ...ed against reverse polarity o Keep the total area of all conductor loops as low as possible in order to reduce the voltages due to indirect lightning strikes o Always carry out a careful final check o...

Page 17: ...LES MegaCell recommends to inspect the installation on a regular basis with following minimum maintenance o Check the electrical and mechanical connections to verify that they are clean secure and und...

Page 18: ...sual appearance of the module surface and result in decreased performance o Use of automatic cleaning machines for solar energy systems is at your own risk and is not authorized by MegaCell in any way...

Page 19: ...Document name MCELL_PV_Modules_Installation_Manual_EN_v1 2_20150715 Revision date V1 2 July 2015 www megacell it MegaCell S r l a socio unico A coordinated company part of Mega Group S r l Registered...