Pre drill 

hole

30mm           

screw

19

18

19

18

18

19

18

19

Pre drill 

hole

20mm           

screw

30mm 

screw

Pre drill 

hole

19

Please retain product label and instructions for future reference

             

Step 16

Fix the cover trims around the

building (as shown in the 

illustration ) securing each trim

into place using 3x30mm 

screws.

12x30mm Screws

Step 17

Attach the fascia boards to

the front and rear of the 

building using 3x40mm

screws per fascia.

*Ensure to screw through

the boards into the 

framing.

24x40mm Screws

Pre drill 

hole

40mm           

screw

Step 18

Fix the barge boards to

the front of the building 

using 3x20mm screws 

per board.

9x20mm Screws

Step 19

Place the Cloaking Strip to the 

rear of one of the doors. Fixing in 

position screwing through the door  

into the cloaking strip with 3x30mm

screws.

Align the tower bolts onto the

vertical framing of the slave

door, secure the bolts to the

top and bottom using 6x30mm

black screws per tower bolt.

Mark the position of the bolt

& drill a hole above and below

for the bolt to catch in to.

15x30mm Black Screws

17

17

16

23

20

Summary of Contents for 01GRODB1008-V4

Page 1: ...based treatment this only helps to protect the product during transit and for upto 3 months against mould To validate your guarantee and ensure longevity of the product it is ESSENTIAL the building is...

Page 2: ...ve transportation blocks from the bottom of each panel before beginning assembly Each Panel should have two blocks 20mm Screw x22 PI 07 0191 P 2 01GRODB1008 V4 Overall Dimensions Length 3055mm Width 2...

Page 3: ...lustration and fix in place using 40mm screws 6x40mm Screws Pre drill hole 40mm screw 14 13 13 Step 3 Fix the door strips onto the front gable using 4x30mm screws for each strip Ensure that there is a...

Page 4: ...a P 4 Please retain product label and instructions for future reference Pre drill hole Pre drill hole Step 7 Place the cover strip 13mm above the gap in the window panel and fix into place using 3x30m...

Page 5: ...a tongue and groove fixing 8x50mm Screws 7 7 Step 9 Place the assembled plain gable and first plain side onto the floor and fix in place Fix the corners with 50mm screws Do not secure the building to...

Page 6: ...3 Place the lrg roofs onto the gables as shown in the illustration Ensure the roof framing sits into the cut out sections and rest on the framing Fix each sml roof section to the gable using 7x30mm sc...

Page 7: ...scia Ensure to screw through the boards into the framing 24x40mm Screws Pre drill hole 40mm screw Step 18 Fix the barge boards to the front of the building using 3x20mm screws per board 9x20mm Screws...

Page 8: ...12x20mm Screws 26 Step 22 Attach the turn buttons to the top and bottom of the slave door using 1x30mm black screw per turn button Ensuring the turn buttons catch the master door 2x30mm Black Screws...