Step 17

Cut the felt into 3 strips of 

3100mm length and place 

onto the roof, as shown in 

the illustration.

Fix the sheets into place

using 132x felt tacks

approximately 100mm

apart.

Felt 

tacks 

P 6

Please retain product label and instructions for future referenc

Please retain product label and instructions for future reference

Step 14

Repeat Steps 11, 12 & 13 to

finish building the roof support.

4x40mm Screws

16x50mm Screws

Pre drill 

hole

40mm 

screw

50mm 

screw

13

8

Step 15

Place the first roof sheet on to

the building, securing in place

with 11x30mm screws.

 

Fix the first eaves frame

 

onto the roof sheet,

 

seceuring with 3x30mm

 screws.

Fix the remaining roof sheets to

the building using 11x30mm

screws per sheet.

 

Fix the next eaves frame

 

to the roof with 3x30mm

 screws.

 

Secure the remaining eaves

 

frame to the center using

 

6x30mm screws.

64x30mm Screws

c

c

Pre drill 

hole

30mm 

screw

*Repeat this process for both sides of the building, ensuring

the roof sheets are flush to the top of the building and sit 

tight together.

Step 16

 

Secure the building to

 

the floor using 38x50mm

 screws.

*Ensure to screw through the

framing into the floor bearers.

38x50mm Screws

Pre drill 

hole

50mm 

screw

HANDLE

WITH CARE

1

2

3

4

13

13

Summary of Contents for 03VER1008-V2

Page 1: ...tended periods of rain swelling of the wood panels may occur Warping of the wood may also occur during excessive dry spells due to an interior moisture loss Unfortunately these processes cannot be avo...

Page 2: ...anel Right AI 03VERWPR2310X2007 V1 Window Panel Left AI 03VERWPR2310X2007 V1 Back Panel QTY 2 AI 03VERBP1490X2015 V1 Gable Top QTY 2 AI 03VERGT2310X546 V1 Floor QTY 2 AI 01TAGF2360X1487 V1 Roof Sheet...

Page 3: ...re fixing to the door Fix the door handles to the outside of the master and slave door using the 35mm bolts provided 36x10mm Screws 4x25mm Screws 4x35mm Bolts Pre drill hole 10mm screw 25mm screw 24 S...

Page 4: ...roof is fitted 9x50mm Screws Pre drill hole 50mm screw 5 4 Step 8 Place the gable tops onto the window panels ensuring the boards interlock Secure in place using 4x50mm screws per gable top screwing...

Page 5: ...s into the ridge bar with 1x50mm screw per bar screwing at an angle as shown in the illustration Ensure to stagger the screws so as not to hit one screw with another 2x50mm Screws Pre drill hole 50mm...

Page 6: ...o the building securing in place with 11x30mm screws Fix the first eaves frame onto the roof sheet seceuring with 3x30mm screws Fix the remaining roof sheets to the building using 11x30mm screws per s...

Page 7: ...s to the front and back of the building using 12x40mm screws 12x40mm Screws Pre drill hole 40mm screw Step 20 Fix the rain guards above each window securing in place using 2x50mm screws per guard ensu...

Page 8: ...piece of framing should fit tightly between the two side panels Step 23 Screw through the side panel exter nally in line with the 2 x 1 framing using 2 x 70mm screw in either side to secure the frami...

Page 9: ...ommended that after the construction treatment and the removal of the protective window cover that sealant is used to keep the building weather tight 30mm screw 28 28 Step 24 Attach a strip to the hin...

Reviews: