background image

P 7

Please retain product label and instructions for future reference

             

Step 8 

(See Pre-Assembly)

Parts needed - No. 8 QTY 12

 

 

No. 9 QTY 12

 

 

No. 10 QTY 6

 

 

No. 12 QTY 12

 

 

No. 13 QTY 6

Following the same method

outlined in 

Pre-Assembly

, lay

the remaining boards 

(No’s. 8, 

9, 10, 12 & 13)

 onto the 

assembly to bring the board 

level to the top of the window 

and door frames.

*Ensure that the boards are

level and flush with each

other as you lay each one.

*Doors can be hung once the 

boarding has enclosed the 

door frame.

3

3

6

6

10

11

Step 9 

(See Pre-Assembly)

Parts needed - No. 6 QTY 2

 

 

  No.10 QTY 2

  

  No. 11 QTY 1

 

Following the same method

outlined in 

Pre-Assembly

, lay

the last two boards (

No. 6 & 

10

)

 

and the board to go above 

the door 

(No. 11) 

onto the 

assembly. 

*Ensure that the boards are

level and flush with each

other as you lay each one.

Step 10 

(See Pre-Assembly)

Parts needed - No. 3  QTY 2

Place the gable tops onto the 

assembly. Fix into position by 

screwing through the notches 

as shown in the illustration. 

*Ensure that the boards are

level and flush with each

other as you lay each one.

4x70mm Screws 

Pre drill 

hole

70mm 

screw

IMPORTANT: 

Pre-drill before fixing screws.

10

9

9

13

12

13

12

8

8

Summary of Contents for 0628LOG175-V4

Page 1: ...esses cannot be avoided but can be helped It is suggested that the outdoor building is sprayed with water during extended periods of warm sunshine and sheltered as much as possible during rain or snow...

Page 2: ...8x120x2170mm QTY 28 LB28 2170 12 Roof Board 16x121x2114mm QTY 90 MB16 2114 13 Floor Board 16x121x3750mm QTY 42 MB16 3750 14 Bearer 44x44x2318mm QTY 26 F4444 2318 15 Bearer 44x44x3808mm QTY 4 F4444 380...

Page 3: ...assembly Please note Each board interlocks at either end in a staggered pattern Before securing ensure that the boards are fitted properly in their respective tongues and grooves Felt Tacks x 600 70m...

Page 4: ...ge the remaining framing No 15 inside the assembled frame Ensure there is an equal amount of space between each frame Secure each of the frames in place using 2x70mm screws for each side of the bearer...

Page 5: ...and level with the ends of the frame Fix each of the starter boards to the frame by screwing through the notch into the frame as shown in the illustration 4x70mm Screws IMPORTANT Pre drill before fixi...

Page 6: ...ons for future reference Step 6 See Window Assembly Parts needed No 1 QTY 4 Refer to window assembly instructions to assemble windows Step 7 Parts needed No 1 QTY 4 Ensure that the lip of the window f...

Page 7: ...the door frame 3 3 6 6 10 11 Step 9 See Pre Assembly Parts needed No 6 QTY 2 No 10 QTY 2 No 11 QTY 1 Following the same method outlined in Pre Assembly lay the last two boards No 6 10 and the board t...

Page 8: ...n Once in position fix to each purlin using 4x40mm screws Due to natural occurences of wood shrinkage expansion You maybe required to use the provided spacers and place a space of 2mm to ensure every...

Page 9: ...the log board on one side Continue adding the floor boards internally making sure to interlock each individual board Do NOT secure the boards until the last board has been measured and cut Following t...

Page 10: ...face of the board 48x30mm Screws 30mm screw Pre drill hole Cut to fit Step 16 Parts needed No 23 QTY 8 Once the floor has been laid arrange the closure trim No 23 around the outside edge of floor inte...

Page 11: ...ew Step 19 Parts needed No 22 QTY 8 Arrange the storm braces No 22 around the building internally Place 2x storm braces per side fixing into place using 2x70mm bolts per brace making sure the washer n...

Reviews: