12
OPERATION MANUAL
3.3 CHECKING THE POWER SUPPLY
METALMASTER machines are supplied wired ready to run. Check the specification plate on the
machine to confirm that the voltage is compatible with the local power supply.
The machine must be connected to the power by a qualified and licensed electrician. Warranty
may be voided if it is found that the connection was not carried out by a qualified electrician.
3.2 MACHINE LEVELING
To set your machine up so that it operates to optimum performance, apply the following procedure
After your guillotine has been anchored to a concrete slab floor, it then needs to be leveled. The
leveling is performed using the screws on each pad.(Fig. 3.1). Loosen the hold down bolts and
place a level on the surface of the working table. Tolerances: 1000:0.30mm, for both longitudinal
and transverse.
Metal plates need to be placed under each jacking screw to distribute the load. Once level then
tighten the hold down bolts.
Metal Plate
Jacking Screw
The machine must not rest on supports other
than those defined in Fig. 3.1
Fig. 3.1
Check the rotation of the motor. If the direction does not match the diagram below, isolate the
machine and change the wiring
Page 12
Instructions Manual for HG-4012 (S948)
12/02/2018