20                                                                                                                                                                                                                                                                                                                                                                                               

situation. If find any abnormal things, pls correct it immediately before operation. 

8.4.6

 Adjustment of safety overflow valve 

The overflow adjustment is very important for normal operation of the machine. Pls 

adjust it as per the maximum working pressure. If    it is found that the machine is 

damaged due to that the pressure adjusted data exceeds the maximum data, the 

manufacurer will not be responsible for this kind of problems or loss occurred due to 

incorrect adjustment. 

8.5 The Maitenance of the Machine 

1). Operator should be familiar with the construction and characteristics of the 

machine .The machine is operated by several operators simultaneously , so 

should arrange special person to be in charge of the production .   

2). Never put the hand within the upper and lower blades to avoid hurt.   

3). To prevent accident due to tools and dirty things between knives , there’re 

should no tools and dirty things on the worktable . 

4). You should period check the sharpness of knives , if they become blunt ,you 

should grind or change at once . To grind the knives you should only grind the 

thickness and ensure the thickness of one set knife are same .                     

5). You should period check each part of machine , maintain the cleanness of the 

machine and surround environment and the good insulation of wire . 

6.  To  maintain  filter  in  good  condition  ,  you  should  often  check  and  clean  the 

filter mounted on the suction port of pump . If the filter not in good condition , 

it will effect the life of pump . 

Only fill in the nitrogen inside the nitrogen bag of accumulator.( oxygen is 

prohibited strictly0

). Pls fill in the nitrogen slowly to avoid t he breaking of 

the bag.   

8. To avoid oil leakage, pls tighten the screws at the piping connection after 25 

hours of operation initially. Pls tighten the screws again every 200 hours after 

formal production. 

Summary of Contents for HG3208VR

Page 1: ...19 3 08 HG3208VR HYDRAULIC GUILLOTINE MANUAL S960...

Page 2: ...QC11Y 8X3200 Hydraulic Guillotine shears Operation Manual Serial No Q709103...

Page 3: ...QC11Y Hydraulic Guillotine Shear 1 Contents...

Page 4: ...QC11Y Hydraulic Guillotine Shear 2...

Page 5: ...6 Maximum Cutting Force 280 KN Including the return pressure 7 Maximum Clamping Pressure 280 KN Vary as per the load 8 Maximum Working Pressure of Hydraulic System 18 MPa 9 Adjustment Range of Back ga...

Page 6: ...QC11Y Hydraulic Guillotine Shear 4...

Page 7: ...ting angle increase 4 Back gauge distance decrease 5 Back gauge distance increase 6 emergency stop 7 Oil filling button 8 Main motor stop 9 Main motor start 10 cutting stroke adjustment 11 Adjusting s...

Page 8: ...QC11Y Hydraulic Guillotine Shear 6 4 Hoisting and Installation...

Page 9: ...ends on the earth situation but not less than 500mm The earth pouring work is done by twice pls see the chart After 15 days from the date of first pouring put the machine on the base and adjust horizo...

Page 10: ...of the machine the various valves have been locked properly and tightly Pls do not adjust the handwheel freely to avoid abnormal action of the machine and avoid loss H the air pressure of accumulator...

Page 11: ...e is tested fine under both no load operation and load operation then you can make the machine into formal production If find the machine is abnormal you will have to correct the problems and then put...

Page 12: ...ts the oil compensation of the series oil circuit The procedure is as below turn the switch to adjust mode stamp the foot switch then push the angle increase button When the knife beam moves down to t...

Page 13: ...QC11Y Hydraulic Guillotine Shear 11 overflow valve 5...

Page 14: ...QC11Y Hydraulic Guillotine Shear 12...

Page 15: ...l operators The operators should read this operation manual very carefully and receive training by our plant Operators can run this machine only under approval of our technicians by training People wi...

Page 16: ...QC11Y Hydraulic Guillotine Shear 14 Electric principle print chart 5...

Page 17: ...circuit overload protection SQ1 Limit switch TZ 9208 1 0 1 C Back gauge front limit SQ2 Limit switch TZ 9208 1 0 1 C Back gauge back limit SQ3 Limit switch TZ 9208 1 0 1 C Knife beam upper limit SQ4...

Page 18: ...r TC Transformer JBK5 500VA 415V 220V 24V Supply control circuit power S1 Foot switch JWL1 11 1 0 Control of knife moving down FU1 Fuse box C65N 3PC32A 3P 32A System short circuit protection FU2 Fuse...

Page 19: ...s as below turn the switch to adjust mode adjust knife beam to balance distance between upper and bottom blades is 3 5mm adjust the bolts and nut which support bott 8 1 3 The installation of the blade...

Page 20: ...rication is a must for the proper machine operation and long machine life Pls make good lubrication as per our provided procedures The main areas for lubrication A The guiding rod and thread rod of th...

Page 21: ...ours of operation 4 The hydraulic oil should be qualified and the viscosity is 27 33 5 Pls clean the oil tank thoroughly for every oil changing 8 4 2 Oil filter 1 Use gasoline or other solution to cle...

Page 22: ...d hurt 3 To prevent accident due to tools and dirty things between knives there re should no tools and dirty things on the worktable 4 You should period check the sharpness of knives if they become bl...

Page 23: ...lotine Shear 21 No Item Specification quantity 1 Foundation Bolt M20X500 4 2 Manual oil gun Oil supply 1 cubic mm 1 3 Nitrogen fill tool 1 4 Operation manual 1 5 Quality Certificate 1 6 Foot switch YD...

Page 24: ...st 8 O Ring 10x1 9 2 9 O Ring 11x1 9 2 10 O Ring 12x2 4 2 11 O Ring 16x2 4 5 12 O Ring 24x2 4 5 13 O Ring 30x3 1 10 14 O Ring 35x3 1 4 15 O Ring 40x3 1 5 16 O Ring 45x3 1 20 17 O Ring 50x3 1 4 18 Pad...