Exercise 2: Diagnostic Test
Figure 119-3: Diagnostic test measurement setup
Diagnostic test is a long duration test for evaluating the quality of the insulation
material under test. The results of this test enable the decision to be made on the
preventive replacement of the insulation material.
Method used
Simulated condition
Expected result
Un=5 kV; T = 1 min; AVG=0
Riso = 9,14 GΩ; DAR=1,36; PI=3,66;
DD=5,44
Table 73-3: Diagnostic test measuring setup/result presentation
Measuring procedure
1. Connection set up is the same as it is performed under Exercise 1.
2. Under
MAIM MENU
MEASUREMENTS
menu select
Diagnostic Test
measurement function
Summary of Contents for MI 3298
Page 55: ...Power Network Application Trainer Earthing Grounding network impedance measurement 55 ...
Page 56: ...Power Network Application Trainer Earthing Grounding network impedance measurement 56 ...
Page 124: ...Power Network Application Trainer Earthing Grounding network impedance measurement 124 ...
Page 228: ...MI 3290 Earth Analyser 228 ...
Page 229: ...MI 3280 Digital Transformer Analyser 229 ...
Page 230: ...MI 3280 Digital Transformer Analyser 230 ...
Page 231: ...MI 3250 MicroOhm 10A 231 ...
Page 232: ...MI 3205 TeraOhmXA 5kV 232 ...