Electrical Installation Safety Trainer
AD 1 - MI 3399
95
2
Set the minimum allowed insulation resistance by clicking in the bottom left dark
grey corner.
3
If a schuko commander is to be used, plug the commander into the appropriate
outlet. If the cables are used, connect all cables appropriately
– the PE cable to
the PE conductor, the N cable to Line2 and the L cable to Line1.
During the measurement, check the insulation resistance between all conductors
(L
X
-L
Y
, L-N, L-PE. N-PE).
4
Press the
START
key.
Expected results
Conduct this measurement at the switchboard. After disabling the RCD measure all
possible insulations resistances between all conductors as described above. To verify
all circuits connected to this RCD simply perform all tests on the output side of the
RCD. If all tests pass then insulation is sufficient between all conductors. In such case
the output of the measuring device should show the same result as the picture below.
Summary of Contents for MI 3399
Page 27: ...Electrical Installation Safety Trainer AD 1 MI 3399 27...
Page 46: ...Electrical Installation Safety Trainer AD 1 MI 3399 46 3 Exit settings...
Page 74: ...Electrical Installation Safety Trainer AD 1 MI 3399 74...
Page 197: ...Power and Voltage Quality Trainer AD 2 MI 3399 197 Figure 4 89 Transient Chart view...
Page 204: ...PAT Appliances Machines Safety Trainer AD 3 MI 3399 204...
Page 249: ...PV Photovoltaic Systems Trainer AD 4 MI 3399 249...
Page 250: ...PV Photovoltaic Systems Trainer AD 4 MI 3399 250 AD 4 MI 3399 PV Photovoltaic Systems Trainer...