Power and Voltage Quality Trainer
AD 2
– MI 3399
156
4.3 Exercise 3
– Voltage Swell
In this exercise, we will show how the instrument should be setup in order to capture
and observe a voltage swell. Voltage swell is temporary increase of the voltage
magnitude at a point in the electrical system above given limit. Before start, please set
the switch S2 in the Application Trainer to ON as shown in the table below. The
remaining switches should be set to OFF.
Switch
Description
State
S2
Swell
ON
The Application Trainer will simulate an electrical system with the following
parameters:
Fundamental voltage: 230 V
Fundamental current: 1000 A
Load type: Inductive
Load character: Load (Consumption of electrical power)
Frequency: 50/60 Hz
276 V high, 5 periods long voltage swell is present on phase L1. The swell is
repeated every 10 seconds.
4.3.1 Instrument setup for Swell capturing
The Power Master MI 2892 should be connected to the Application Trainer and set up
as described in section 3.2 Instrument Setup. It is good practice to observe the
Connection Check status in the MEASRUEMENT SETUP
CONNECTION SETUP
menu. If it is marked with an OK sign ( ), you can start observing measurements.
For observing voltage swells, it is necessary to set up a swell threshold voltage. If the
voltage raises above the threshold, the voltage swell will be recorded. Limits are set
up in the MEASRUEMENT SETUP
EVENT SETUP menu as shown in the figures
below.
Figure 4-21: Swell threshold setup
Parameters need to be set:
Swell: 110% - this event will be detected, if an increase of more than 10% of the
nominal voltage occurs on the input channel,
Dip: 90% - this event will be detected, if a drop of more than 10% of the nominal
voltage occurs on the input channel,
Summary of Contents for MI 3399
Page 27: ...Electrical Installation Safety Trainer AD 1 MI 3399 27...
Page 46: ...Electrical Installation Safety Trainer AD 1 MI 3399 46 3 Exit settings...
Page 74: ...Electrical Installation Safety Trainer AD 1 MI 3399 74...
Page 197: ...Power and Voltage Quality Trainer AD 2 MI 3399 197 Figure 4 89 Transient Chart view...
Page 204: ...PAT Appliances Machines Safety Trainer AD 3 MI 3399 204...
Page 249: ...PV Photovoltaic Systems Trainer AD 4 MI 3399 249...
Page 250: ...PV Photovoltaic Systems Trainer AD 4 MI 3399 250 AD 4 MI 3399 PV Photovoltaic Systems Trainer...