15.2
Preventive Maintenance Schedule
Consult the following preventive maintenance schedule for daily, weekly, and monthly maintenance tasks:
Table 3. Recommended Preventive Maintenance Schedule
ITEM
TASK
INTERVAL
MOTORS
GREASE MOTORS OPERATING AT
NORMAL TEMPERATURE
APPLY 1.41 OUNCES (40 G)
2000 HOURS RUN TIME
GREASE MOTORS OPERATING ABOVE 70
C (158 F)
APPLY 0.7 OUNCES (20 G)
1500 HOURS OF RUN TIME
ELECTRICAL
CABLES
CHECK FOR WEAR AND DAMAGE
WEEKLY
SCREEN
GASKETS
CHECK FOR CRACKS
MONTHLY
DECK
ADJUSTMENT
SYSTEM
CHECK FOR FULL UP AND DOWN TRAVEL
MONTHLY
SUPPORT
SPRINGS
CHECK FOR UNEVEN COMPRESSION
MONTHLY
SCREEN HOLD
DOWN BAR
CHECK SCREWS FOR TIGHTNESS
MONTHLY
GASKET
GROMMETS
CHECK FOR HOLDING
MONTHLY
NUTS AND
BOLTS
CHECK FOR TIGHTNESS
MONTHLY
MOTOR BOLTS
VERIFY PROPER TORQUE
MONTHLY
DECK
ADJUSTMENT
SYSTEM
GREASE JACK FITTING
MONTHLY
NOTE