Pumping/Baking the Chamber
Appendix B
Turn off the heat tapes and allow the turbo pump to continue pumping the
chamber for at least 4 hours. Make sure that the test-mass remains locked
until the chamber is completely cool. When the chamber has returned to
ambient temperature, remove the heat tapes and reinstall the ion pump
magnet package.
7.4. Starting the Ion Pump
Install the red magnets on the turbo pump. Check the AC, BAT, and HV
switches on the ion pump power supply, and make sure that they are off.
Connect the ion pump HV cable (#9) to the ceramic connector on the pump.
Connect the small green safety ground umbilical of the HV cable to one of the
banana jacks located on the base of the dropping chamber near one of the
handles. Connect the safety HV ground cable (#10) to the other banana jack
on the base of the dropper. Set the meter select knob on the ion pump
controller to PUMP VOLTAGE (KV). Start the ion pump by turning on the
AC, BAT, and HV switches on the ion pump controller. Leave the turbo
pump running and connected to the dropping chamber until the ion pump
starts. After turning on the ion pump, check the meter on the ion pump
power supply. The voltage should be at least 2 KV within five minutes after
turning on the ion pump. At operating pressure, nominal voltage is 4 KV (on
AC), and 3 KV (on battery). If the ion pump has not started within five
minutes, turn off the power and continue pumping with the turbo pump for
at least one hour before trying the ion pump again. Leaving the ion-pump on
with excessive current (> 10
-5
Torr) shortens the lifetime of the pump
dramatically. After the ion pump has started, close the vacuum valve and
turn off the turbo pump. Once the turbo pump has vented, remove the
flexible hose and replace the blank flanges on the vacuum valve and turbo
pump intake.
7-4
Summary of Contents for FG5
Page 22: ...Design Components and Function 2 Figure 2 10 The Superspring 2 14 ...
Page 31: ...Design Components and Function 2 Figure 2 13 Rotation Monitor 2 23 ...
Page 32: ......
Page 42: ...How to Set Up and Run the FG5 3 3 10 ...
Page 44: ...How to Set Up and Run the FG5 3 Figure 3 2 V Post 3 12 ...
Page 53: ...How to Set Up and Run the FG5 3 1 Backup the data 2 Shut off computer power 3 21 ...
Page 87: ...Adjustment and Maintenance 4 4 29 ...
Page 91: ...Adjustment and Maintenance 4 4 33 ...
Page 104: ...Troubleshooting 5 5 2 ...
Page 117: ...Troubleshooting 5 5 15 ...
Page 131: ...Checklists and Logs Appendix D 9 3 ...
Page 140: ...Checklists and Logs Appendix D Table 9 6 Replacing Drive Belt 9 12 ...
Page 145: ...Checklists and Logs Appendix D Table 9 10 Replace Linear Bearings 9 17 ...
Page 149: ...Checklists and Logs Appendix D Table 9 13 Replace Shaft Encoder 9 21 ...