Checklists and Logs
Appendix D
9.2. FG5 Setup
9-4
FG5 SETUP CHECKLIST
Unpack and assemble interferometer.
Position interferometer over reference mark. Orient so laser is in
the north-south direction, if possible
Set up electronics case and remove covers.
Check AC line voltage. Connect main AC power cable.
Connect signal, HV cables from electronics rack to laser head.
Turn on main AC and DC power switches.
Assemble dropping chamber tripod and place on interferometer.
Place
dropping chamber on tripod, ion pump away from laser head.
Clamp dropping chamber to tripod.
Release cart travel lock.
Connect ion pump cables and start ion pump. Rough pump
dropping chamber, if necessary.
Summary of Contents for FG5
Page 22: ...Design Components and Function 2 Figure 2 10 The Superspring 2 14 ...
Page 31: ...Design Components and Function 2 Figure 2 13 Rotation Monitor 2 23 ...
Page 32: ......
Page 42: ...How to Set Up and Run the FG5 3 3 10 ...
Page 44: ...How to Set Up and Run the FG5 3 Figure 3 2 V Post 3 12 ...
Page 53: ...How to Set Up and Run the FG5 3 1 Backup the data 2 Shut off computer power 3 21 ...
Page 87: ...Adjustment and Maintenance 4 4 29 ...
Page 91: ...Adjustment and Maintenance 4 4 33 ...
Page 104: ...Troubleshooting 5 5 2 ...
Page 117: ...Troubleshooting 5 5 15 ...
Page 131: ...Checklists and Logs Appendix D 9 3 ...
Page 140: ...Checklists and Logs Appendix D Table 9 6 Replacing Drive Belt 9 12 ...
Page 145: ...Checklists and Logs Appendix D Table 9 10 Replace Linear Bearings 9 17 ...
Page 149: ...Checklists and Logs Appendix D Table 9 13 Replace Shaft Encoder 9 21 ...