Adjustment and Maintenance
4
Steering the beam onto the APD: The beam can be steered onto the APD
using the mirror mount holding the APD focusing lens. You should notice
that the beam is either on or off of the sensitive APD area (there is not a sharp
maximum, but a rather flat response) as you sweep the beam across the APD.
On most APD boards, the voltage is negative when light hits the APD. You
can verify this by blocking off the light using the REF BEAM beam-blocker.
Focusing the beam on the APD: Change the focus of the APD until the
maximum light level is reached. This focus adjustment is not very sensitive,
so sometimes it is useful to note the two positions of the lens where the light
level decreases by a fixed amount and then set the lens to the mid-position for
the maximum level. Tighten the locking nut for the focusing lens.
4.2.2.15.Adjusting The Fringe Amplitude
Put the dropper/tripod back on the interferometer base. Level the
interferometer base to the bubble levels on the dropper and raise the tripod
by one full turn of the tripod feet. Mount the Superspring. Align the test
beam and reference beam in the fringe viewer. Put the dropper into OSC
mode and maximize the fringes using the last mirror adjustment and
twiddler underneath the interferometer base. Do not forget to lock the laser.
Once the fringes are maximized, you should adjust the
λ
/2 plate (or optical
isolator) so the fringes are as large as possible without clipping on the edges.
When the light level is too high, the amplifier will saturate, producing a
flattened or clipped response instead of the usual sine-wave fringes that
should be produced. Once this light level has been adjusted, tighten the
screws holding the
λ
/2 plate (or optical isolator). Use a M2.5 hex socket
wrench for the
λ
/2 plate or a M3 wrench for the optical isolator.
4.2.2.16.Replace all covers and tighten all screws
4-17
Summary of Contents for FG5
Page 22: ...Design Components and Function 2 Figure 2 10 The Superspring 2 14 ...
Page 31: ...Design Components and Function 2 Figure 2 13 Rotation Monitor 2 23 ...
Page 32: ......
Page 42: ...How to Set Up and Run the FG5 3 3 10 ...
Page 44: ...How to Set Up and Run the FG5 3 Figure 3 2 V Post 3 12 ...
Page 53: ...How to Set Up and Run the FG5 3 1 Backup the data 2 Shut off computer power 3 21 ...
Page 87: ...Adjustment and Maintenance 4 4 29 ...
Page 91: ...Adjustment and Maintenance 4 4 33 ...
Page 104: ...Troubleshooting 5 5 2 ...
Page 117: ...Troubleshooting 5 5 15 ...
Page 131: ...Checklists and Logs Appendix D 9 3 ...
Page 140: ...Checklists and Logs Appendix D Table 9 6 Replacing Drive Belt 9 12 ...
Page 145: ...Checklists and Logs Appendix D Table 9 10 Replace Linear Bearings 9 17 ...
Page 149: ...Checklists and Logs Appendix D Table 9 13 Replace Shaft Encoder 9 21 ...