6
Midco
International
Inc.
8471 15
MADE
in the
USA
Part 1 Installation
13. Start and stop the burner several times to check its operation with the charging door open, and
then with it closed. Remove any temporary Door Open
bypasses installed in Step 6.
14. Test operation of any auxiliary operating and/or limit controls.
15. Load incinerator and make trial run. Confi rm that the incineration chamber pressure stays within
the range of 0 to minus 0.5″ W.C.
16.
WARNING: When the incinerator is located inside a building and a draft control is
used, check that there is no spillage of fl ue products from the draft control.
17. To shut off : Turn Burner Switch or Timer off and close Main Manual Shut -Off Valve
VII Initial Start
Up/Adjustment
Continued
120V
10
BL/W
IMPORTANT: IF REPLACING USE ONLY
3 AMP FUSE.
SCHEMATIC
LEGEND
S
BK