Perform the electric safe check after completing installation:
1. Grounding work 
    After finishing grounding work, measure the grounding resistance by visual detection and 
    grounding resistance tester. Make sure the grounding resistance is less than 4

Ω

2. Electrical leakage check (performing during test running)
    During test operation after finishing installation, the serviceman can use the electroprobe 
    and multimeter to perform the electrical leakage check. Turn off the unit immediately if 
    leakage happens. Check and find out the solution ways till the unit operate properly.

A: Lo packed valve  B: Hi packed valve 
C and D are ends of indoor unit connection.

CAUTION

Indoor unit
check point

D

B

C

A

Outdoor unit
check point

Cover

Fig.27

 

  Electrical safety check

 

  Gas leak check

1. Soap water method:
     Apply a soap water or a liquid neutral detergent 
     on the indoor unit connection or outdoor unit 
     connections by a soft brush to check for leakage 
     of the connecting points of th piping. If bubbles
     come out, the pipes have leakage.
2. Leak detector

Use the leak detector to check for leakage.

Test running

Safety and leakage check

14

 TEST RUNNING

Manual control 

button

AUTO/COOL

Perform  test operation after completing gas leak check at the flare nut connections and 
electrical safety check.
    Check that all tubing and wiring have been properly connected.
    Check that the gas and liquid side service valves are fully open.
1. Connect the power, press the ON/OFF button on the remote controller to turn the unit on.
2. Use the MODE button to select COOL, HEAT, AUTO and FAN to check if all the functions
     works well. 

O

3. When the ambient temperature is too low(lower than 17 C), the unit cannot be controlled by 
     the remote controller to run at cooling mode, manual operation can be taken. Manual 
     operation is used only when the remote controller is disable or maintenance necessary.
     Hold the panel sides and lift the panel up to an angle until it remains fixed  with a clicking 
     sound.
     Press the Manual control button to select the AUTO or COOL, the unit will operate under 
     Forced AUTO or COOL mode(see User Manual for details).
4.  The test operation should last about 30 minutes.

Summary of Contents for INVERTER SPLIT TYPE ROOM AIR CONDITIONER

Page 1: ...ompletely before installing the product If the power cord is damaged replacement work shall be performed by authorised personnel only Installation work must be performed in accordance with the nationa...

Page 2: ...use by persons including children with reduced physical sensory or mental capabilities or lack of experience and knowledge unless they have been given supervision or instruction concerning use of the...

Page 3: ...ring standard regulation and this installation instructions An independent circuit and single outlet must be used If electrical circuit capacity is not enough or defect found in electrical work it wil...

Page 4: ...ated by arrows from wall or other obstacles Do not place animals and plants in the path of the air inlet or outlet Take the air conditioner weight into account and select a place where noise vibration...

Page 5: ...e 60c m abo ve 30cm above Air Filter Air Outlet 30cm above Wrapping tape B 200cm above Additional drain pipe Accessories Parts you must purchase Consult the dealer about the pipe size 6 35 9 53 12 7 9...

Page 6: ...mensions are in mm unless otherwise stated 1 Determine hole positions according to the diagramdetailed in Fig 5 Drill one 1 hole 65mm slanting slightly to outdoor side 2 Always use wall hole conduit w...

Page 7: ...the indoor unit with a cushioning material between the indoor unit and the wall Get it out after finish piping 4 Push the lower part of the indoor unit up on the wall then move the indoor unit from s...

Page 8: ...se sloped downward to drain out the condensed water smoothly CAUTION Install the outdoor unit on a rigid base to prevent increasing noise level and vibration Determine the air outlet direction where t...

Page 9: ...r tube pipe in a downward direction as you remove burrs in order to avoid dropping burrs into the tubing Pipe Reamer Point down Fig 16 Fig 17 Outdoor unit dimension mm WxHxD A mm B mm 530 290 484 600...

Page 10: ...air conditioner and explain to the client until the problem is solved 2 Power voltage should be in the range of 90 110 of rated voltage 3 The creepage protector and main power switch with a 1 5 times...

Page 11: ...oosening the screw as shown in Fig 22 4 Ensure the colour of wires of outdoor unit and the terminal Nos are the same to the indoor s respectively 5 Wrap those cables not connected with terminals with...

Page 12: ...connecting means must be provided and shall be located within sight from and readily accessible from the air conditioner Connecting cable with conduit shall go through the hole of the conduit panel No...

Page 13: ...the fixed wiring and have an air gap contact separation of at least 3mm in each active phase conductors CAUTION CAUTION CAUTION CAUTION Air and moisture in the refrigerant system have undesirable eff...

Page 14: ...ully open the handle Lo of the manifold valve 4 Operate the vacuum pump to evacuate After starting evacuation slightly loose theflare nut of the Lo valve on the gas pipe side and check that the air is...

Page 15: ...If bubbles come out the pipes have leakage 2 Leak detector Use the leak detector to check for leakage Test running Safety and leakage check 14 TEST RUNNING Manual control button AUTO COOL Perform tes...

Page 16: ...CS120I BP9A1 LH 202000192327 20110613 The design and specifications are subject to change without prior notice for product improvement Consult with the sales agency or manufacturer for details...