the 2-way valve approximately 45’ for 3 seconds then closing it for 1 minute; repeat 3 times.
After purging the air, use a torque wrench to tighten the flare nut on the 2-way valve.
4). Check the gas leakage
Check the flare connections for gas leakage.
5). Discharge the refrigerant.
Close the valve on the charging cylinder and discharge the refrigerant by loosening the flare nut on the
2-way valve approximately 45’ until the gauge indicates 0.3 to 0.5 Mpa.
6). Disconnect the charge set and the charging cylinder, and set the 2-way and 3-way valves to the open
position
Be sure to use a hexagonal wrench to operate the valve stems.
7). Mount the valve stems nuts and the service port cap
Be sure to use a torque wrench to tighten the service port cap to a torque 18N.m.
Be sure to check the gas leakage.
7.7 Re-installation while the outdoor unit need to be repaired
1. Evacuation for
the whole system
Procedure:
1).
Confirm that both the 2-way and 3-way valves are set to the opened position.
2). Connect the vacuum pump to 3-way valve’s service port.
3). Evacuation for approximately one hour. Confirm that the compound meter indicates -0.1Mpa.
4). Close the valve (Low side) on the charge set, turn off the vacuum pump, and confirm that the gauge
needle does not move (approximately 5 minutes after turning off the vacuum pump).
5). Disconnect the charge hose from the vacuum pump.
2. Refrigerant charging
Summary of Contents for MOAB01-07HN1
Page 12: ...Mission On off DM16 01 01 21en 12 Service manual For MSMBA 07HRN1 W MSMBA 09HRN1 W...
Page 13: ...DM16 01 01 21en Mission On off Service manual 13 For MSMBB 12HRN1 W For MSMBC 19HRN1 W...
Page 14: ...Mission On off DM16 01 01 21en 14 Service manual For MSMBD 24HRN1 W...
Page 16: ...Mission On off DM16 01 01 21en 16 Service manual For MOAB01 07HN1 MOAB01 09HN1...
Page 18: ...Mission On off DM16 01 01 21en 18 Service manual For MOCA01 24HN1...