Step 1:

Prior to unpacking equipment please inspect boxes for any transport damage to ensure products are in perfect condition.

Step 2

: Ensure the equipment model numbers on the boxes correspond with your companies purchase order.

Step 3:

Unpack the equipment and ensure all parts are accounted for i.e Indoors / Outdoor / Hard Wired & Infra-red Controllers.

Step 4:

Store the Infra-red service controller safely as this can be used to speed up commissioning and servicing process.

Step 5:

Review the installation and maintenance manuals which are provided.

Step 6:

Carry out the positioning and installation of indoor and outdoor units as per guidelines within the installation manual.

Step 7:

Install refrigerant pipework (Purge with OFN while brazing), electrical wiring & drainage pipe work.

Step 8:

Interconnecting control wiring between indoor and outdoor units is made by linking into terminals S1 & S2.

Step 10:

Set master & Slave indoor via SW5.

Step 9:

Connecting of the Hard-Wired controller is made by linking to CN40 on the Master indoor PC Board in first indoor

Step: 10:

Set auto restart function by setting SW3 on indoor unit to on position.

Step 11:

Pressure test pipework (Note do not carry out pressure test while connected to outdoor unit to prevent contamination of factory charge)

(1) Strength test in 5 Bar increments up to full test pressure. (2) Then leak test at lower pressure. Evacuate system to 2 torr or lower for appropriate
time.

Step 12:

If required please add additional refrigerant charge (see table on reverse).

Step 13:

Carry out all the commissioning checks required to activate the warranty of the newly installed system.

Step 14:

Perform the test operation in accordance with the installation manual to ensure all functions and parts are working correctly.

Step 15:

Complete your warranty card document and e-mail this with dated photo of outdoor serial number to:

info@fgeuropeuk.co.uk

Note:

Installation videos can also be found on the Midea UK YouTube channel.

S1 & S2

(Interconnecting Wiring)

Indoor

Outdoor

SW3

(Auto Restart)

j

MI GUIDE

R410a Twin Floor & Ceiling Series Installation

Please contact your Midea support team if you have any issues during the installation and commissioning process.

Midea UK Tel:

0191 263 6367

Reviews: