MNChinook 200M Instructions

 

 

  SAFETY 

 
Safety must always be your primary concern during the assembly, installation and operation of your 

Chi-

nook 200M 

turbine. Always be aware of the risks involved with mechanical and electrical installation work. If 

in doubt about any issue regarding your turbine, please seek further assistance before proceeding.   

Mechanical Safety Hazards 

 

 

The main rotor is the most obvious and serious mechanical safety risk. When the turbine is oper-
ating at its rated speed, the blades will be very difficult to see due to the rotation speed. Never 
approach the turbine while it is operating. Always shut down the turbine by activating the stop 
switch. 

Ensure that the turbine is installed in a suitable location where nobody can approach 

or interfere with the path of the rotor blades. 

 

 

Working with tools of any kind can be dangerous. Your 

Chinook 200M

 turbine requires some basic 

mechanical assembly with rudimentary hand tools. If you are in any doubt about how to use these 
tools correctly, please seek advice from an experienced person.   

 

Your 

Chinook 200M 

turbine will inevitably be installed upon a mast, tower or other mount. This may 

mean working at height. Always ensure that all personnel in the immediate vicinity are aware of any 
lifting / hoisting operations that will be occurring. Check there are no loose components or tools 
likely to fall and cause injury during the lifting operation. Where possible, all assembly work should 
be completed at ground level. 

 

Ensure that the batteries are disconnected during the installation procedure.   

 

Twist the turbine output wires together (to create a short circuit) during the mechanical installation 
pr

ocess. This will prevent the turbine from ‘spinning up’ during the installation.   

 

Never install the turbine upside down or in any orientation other than that depicted on the installa-
tion instructions.   

 

Install your turbine during a calm day.   

 

When performing routine inspection or maintenance, always stop the turbine by activating a stop 
switch or by shorting out the turbine output once disconnected from the battery.   

 

Electrical Safety Hazards 

 

 

The 

Chinook 200M 

generates rectified DC voltage. Even at these low voltages there are inherent 

risks. Caution should always be used when connecting the 

Chinook 200M

 to the electrical system.   

 

Ensure that you have followed the wire-sizing chart to ensure that the correct size of wire has been 
selected. If wire of insufficient size is used, heat will build up in the wires causing a potential fire 
hazard. A properly sized fuse or circuit breaker must be used in the wires connected to the battery. 
This will stop the risk of short circuit currents and fire.   

 

Batteries used in renewable energy systems can deliver a serious amount of current. A short circuit 
in the battery circuit can lead to hundreds of amps flowing through the battery cables. This will 
cause a heat buildup and ultimately an electrical fire. Batteries are also susceptible to explode 
when shorted. Always use insulated electrical tools when working on the battery’s electrical 
connections. Removing rings and jewelry is also a good idea. 

 

Batteries are very heavy. Do not attempt to move batteries by yourself. Always use manual han-
dling tools and an assistant.   

 

Always keep lead-acid batteries the correct way up. Do not allow the acidic electrolyte to spill or 
come into contact with your skin or face. Always follow the 

manufacturer’s safety instructions when 

handling lead-acid batteries.   

 

Please use common sense when installing and operating your turbine!   

Summary of Contents for Chinook 200 Marine

Page 1: ...e clean renewable electricity anywhere the wind blows Available in 12 24 and 48 Volt models Innovative design axial flux alternator using neodymium iron boron magnets Powder coated stamped aluminum ch...

Page 2: ...nook 200M Instructions Contents Disclaimer 3 Introduction 3 Safety Precautions 4 Specifications 5 Package Contents 6 Mechanical Assembly 7 Electrical Installation 11 Turbine Operation 14 Maintenance 1...

Page 3: ...USA by MidNite Solar Inc 17722 67 th AVE NE Arlington WA 98223 PH 360 403 7207 Fax 360 691 6862 www MidniteSolar com Introduction Please read this manual thoroughly before attempting to assemble insta...

Page 4: ...l installation process This will prevent the turbine from spinning up during the installation Never install the turbine upside down or in any orientation other than that depicted on the installa tion...

Page 5: ...INOOK200M Nominal Voltage 12 24V 48V DC Rotor Blades Glass Reinforced Nylon Rotor Diameter 1 Meter 3 28 Feet Rated Wind Velocity 14m s 31 30 mph Rated Output 200 Watts Max Output 250 Watts Start up Wi...

Page 6: ...o come Package Contents Your Chinook 200M Turbine will arrive containing the components shown below If any of the components are missing or damaged please contact your dealer immediately 3 Blades 1 Tu...

Page 7: ...tely 100 hours of normal operation for the bearing seals to Break in and the lubrication to be distributed correctly around the bearing raceways and ball cages During this period you may notice a redu...

Page 8: ...skin Rotor Blade Assembly Take the three rotor blades and rotor hub plate Be careful when handling the blades they may have sharp edges Use a 10mm socket hexagon key and three M6 x 18mm long cap screw...

Page 9: ...spaced equally Fit the Rotor Blade Assembly The assembled and balanced rotor blades can now be fitted to the Chi nook 200M chassis This is done by placing the rotor hub plate against the bearing hous...

Page 10: ...and batteries will be located Follow the table below to select the correct wire size This will vary depending on your nominal battery voltage and the distance that the cables will be run Careful selec...

Page 11: ...e may be different ways of wiring small wind turbines photovoltaic panels charge controllers and batteries together This type of system will often expand organically but the following guidelines shoul...

Page 12: ...inst the buildup of static and lightning strikes The turbine mount should be grounded separately with its own ground rod and an appropriate surge arrestor installed to help prevent damage to the batte...

Page 13: ...ries are fully charged or not Depending on the size of the dump load the turbine may slow down or stall during a period when the power is being diverted Larger capacity battery banks will be able to s...

Page 14: ...acceptable limits the CDL will stop diverting current to the dump load Refer to the CDL controller user manual for specific operating instructions Shut Down By activating the optional stop switch if...

Page 15: ...w set of rotor blades should be installed Contact MidNite Solar for replacements Inspect the roots of the blades attachment tabs for signs of stress cracking or fatigue A new set of rotor blades shoul...

Page 16: ...inook 200M turbine Rotor Blades sold only in sets of 3 Slip Ring Wiper set of 2 Slip Ring sold only with yaw mount assembly Stator 48VDC Stator 24VDC Stator 12VDC Bridge Rectifier Yaw Bearing Housing...

Page 17: ...umber issued by MidNite Solar For an RMA number contact MidNite Solar Inc 17722 67th Ave NE Arlington WA 98223 360 403 7207 Purchasers must prepay all delivery costs or shipping charges to return any...