Typical wire routing between E-Panels.
Refer to the appropriate wiring diagram for your system.
In the example above L2OUT goes from the transfer breakers on the master to the L2OUT busbar on the
slave unit, L2IN goes from the L2IN busbar on the master unit to the L2IN busbar on the Slave unit, all
in the lower conduit. The ground can be in either conduit as is convenient. The inverter communication
cable is routed through the upper conduit.
*Ground wire may be routed through either conduit.
Power and communication wiring should be kept separate.