Preparing the electrical connection
^
Remove the cover of the terminal
box.
^
Decide whether you would like the
power cable to enter the ventilation
system from below or from the rear.
Remove the respective knock-out.
^
If the system is connected to an
external blower, remove the
knock-out for the control cable.
^
Install a suitable UL listed cable
clamp or conduit fitting (not included)
in the knock-out.
^
With the assistance of at least one
other person, lift the ventilation
system into the prepared cutout. The
top mounting angles should rest on
the countertop.
^
Align the ventilation system.
^
Secure the appliance to the floor and
the countertop.
^
Remove the protective plastic from
the side cover.
^
Push the side covers in place on the
mounting brackets and engage them.
Installation
32
Summary of Contents for DAG 1000
Page 8: ...Description of the appliance 8 ...
Page 16: ...16 ...
Page 18: ...18 ...
Page 20: ...Appliance dimensions 20 ...
Page 22: ...Cabinet dimensions Appliance dimensions 22 ...
Page 39: ...39 ...