Cylinder Installation
PELLERIN MILNOR CORPORATION
Figure 2: Detailed views
Legend
A.
Top connection between the shell front and the shell side sheet
B.
Bottom connection between the shell front and the shell side sheet
C.
Connection between the shell rear and the bearing housing
D.
Connection between the Pull-up plate and the Hub (outer bolts)
E.
Connection between the Pull-up plate and the Shaft (inner bolts)
M.
Use thread lock compound Locktite 242. If Item 8 has coarse threads, tighten to 1817 FT.LBS. If item 8 has fine
threads, tighten to 2012 FT. LBS. (See
N.
Use thread lock compound Locktite 242. Tighten items 14 and 15 to 376 FT. LBS. ( 4 instances).
P.
Apply silicone to the hub side of the gasket.
Q.
0.25 inches [6.3mm].
R.
Use thread lock compound Locktite 242. Tighten items 16 and 17 to 36 IN. LBS. (18 instances).
S.
Use thread lock compound Locktite 242. Torque items 20 and 15 to 376FT. LBS. ( 4 instances).
T.
Apply oil to the o-rings before you assemble.
.
78
Summary of Contents for 48040M7K
Page 2: ......
Page 8: ......
Page 9: ...Safety 1 5 ...
Page 43: ...Installation 2 39 ...
Page 56: ......
Page 57: ...Drive 3 53 ...
Page 59: ...Drive Components and Belt Installation PELLERIN MILNOR CORPORATION Figure 2 Detailed views 55 ...
Page 93: ...Frame and Tilt 4 89 ...
Page 101: ...Hydraulic Assemblies 5 97 ...
Page 110: ......
Page 111: ...Door Assemblies 6 107 ...
Page 125: ...Water and Steam 7 121 ...
Page 137: ...Chemical 8 133 ...
Page 142: ......
Page 143: ...Control and Sensing Assemblies 9 139 ...
Page 149: ...Dimensional 10 145 ...
Page 150: ......
Page 151: ...147 ...