5.5.1 Filling Solution Tank
Fill solution tank (Fig. 8/1) before work or as
required. Park machine on level ground.
Open tank lid (Fig. 8/5) and fill tank up to the
maximum (1/1 marker) (Fig. 8/2).
Alternatively, filling of the machine via quick
coupling (Fig. 8/6) is available. Before doing
so, connect the filling hose of the dosage
unit and the quick coupling. The floater valve
automatically closes after the maximum
filling level has been attained.
(Refer to specific operating instructions for
information on operation of the dosage unit)
The maximum admissible service pressure
of the floater unit is 87psi.
5.5.2 Emptying Solution Tank
Park machine such that the fill level hose
(Fig. 8/3) is located above the drain aperture
in the floor. Take fill level hose from holder
and remove lid.
5.5.3 Solution Filter
Check solution filter (Fig. 8/4) at weekly
intervals and clean or replace if required.
1 Empty solution tank (Fig. 8/1), see para-
graph 5.5.2.
2 Unscrew filter cap.
3 Remove the filter element from the filter
case for cleaning. Replace if required.
4 Re-install filter element and filter cap.
Only clean solution filter when the
solution tank is empty.